719 1/2 E SUNSET AVE 90291

Certificate Information: 719 1/2 E SUNSET AVE 90291

Application / Permit
20016-30000-17435
Plan Check / Job No.
B20WL03099
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) RECREATION ROOM INTO ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 7/16/2021
Issuing Office
Current Status
CofO Issued on 12/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 KAVIAN REFAHI
Corrections Issued 7/24/2020 KAVIAN REFAHI
Building Plans Picked Up 7/28/2020 APPLICANT
Applicant returned to address corrections 6/9/2021 KAVIAN REFAHI
No Progress 6/30/2021 ALFREDO JARA
Plan Check Approved 6/30/2021 ALFREDO JARA
No Progress 7/16/2021 KAVIAN REFAHI
Plan Check Approved 7/16/2021 KAVIAN REFAHI
Issued 7/16/2021 APPLICANT
CofO in Progress 12/14/2021 DAVID FEILER
Permit Finaled 12/16/2021 DANIEL ORRANTE
CofO Issued 12/16/2021 DANIEL ORRANTE
Permit Finaled 12/16/2021 DANIEL ORRANTE

Permit Application Clearance Information

Tenant Habitability Plan Cleared 8/14/2020 MICHAEL SOTO
Address approval Cleared 8/18/2020 KATHLEEN LEE
Eng Process Fee Ord 176,300 Cleared 8/18/2020 KATHLEEN LEE
Sewer availability Cleared 8/18/2020 KATHLEEN LEE
Specific Plan Cleared 8/25/2020 FREDDY GARCIA
Specific Plan Cleared 8/25/2020 FREDDY GARCIA
ZA Case Cleared 8/26/2020 ANACANY HURTADO
ZA Case Cleared 8/26/2020 ANACANY HURTADO
Hydrant and Access approval Cleared 9/24/2020 KURT CORRAL
Coastal Zone Cleared 5/24/2021 KENTON TRINH
Coastal Zone Cleared 5/24/2021 KENTON TRINH
Specific Plan Cleared 5/24/2021 KENTON TRINH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2021 Approved JOHNNY MIRANDA
Special/Order Compliance 9/9/2021 No Access for Inspection KENNETH NAGLE
Pre-Inspection 9/13/2021 Approved JOHNNY MIRANDA
Special/Order Compliance 9/13/2021 Partial Inspection KENNETH NAGLE
Pre-Inspection 11/10/2021 Corrections Issued DAVID FEILER
Rough-Elec/Plmb/HVAC 11/16/2021 Approved DAVID FEILER
Special/Order Compliance 11/16/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 12/1/2021 Approved ENRIQUE MIRELES
Final 12/1/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/1/2021 Approved ENRIQUE MIRELES
Green Building Rough 12/1/2021 Approved ENRIQUE MIRELES
Smoke Detectors 12/1/2021 Approved ENRIQUE MIRELES
Final 12/14/2021 OK to Issue CofO DAVID FEILER