2824 S STONER AVE 90064
Certificate Information: 2824 S STONER AVE 90064
- Application / Permit
- 20016-30000-17364
- Plan Check / Job No.
- B20WL03088
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) garage to an accessory dwelling unit per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/20/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | JASON JANGADA |
| Corrections Issued | 9/26/2020 | JASON JANGADA |
| Applicant returned to address corrections | 11/12/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 12/1/2020 | JASON JANGADA |
| Plan Check Approved | 1/27/2021 | JASON JANGADA |
| Issued | 2/20/2021 | APPLICANT |
| Building Plans Picked Up | 2/24/2021 | APPLICANT |
| CofO in Progress | 4/11/2022 | JOHNNY MIRANDA |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
| CofO Issued | 4/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2020 | SAUL GARCIA |
| Sewer availability | Cleared | 10/16/2020 | SAUL GARCIA |
| Hydrant and Access approval | Cleared | 10/23/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 12/13/2020 | RIDWAN HARDY |
Contact Information
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/18/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 5/5/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/25/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/15/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 6/22/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 7/9/2021 | Partial Approval | DONALD GALLAGHER |
| PLUMBING-Rough | 8/2/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 8/4/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/6/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 9/9/2021 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/16/2021 | Conditional Approval | EVAN COOPER |
| ELECTRICAL-Rough | 9/16/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 9/16/2021 | Approved | EVAN COOPER |
| Underground Mechanical | 9/24/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/1/2021 | Partial Approval | KENNETH NAGLE |
| Insulation | 10/14/2021 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 10/25/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 10/29/2021 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/3/2021 | Approved | RYAN SALAZAR |
| Shower Pan | 11/3/2021 | Approved | RYAN SALAZAR |
| Gas Test | 3/15/2022 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | JOHNNY MIRANDA |
| Final | 3/23/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 3/23/2022 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 3/23/2022 | Approved | JOHNNY MIRANDA |
| Final | 3/29/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 3/29/2022 | Approved | JOHNNY MIRANDA |
| Final | 4/8/2022 | OK to Issue CofO | JOHNNY MIRANDA |