4116 W 30TH ST 90016

Certificate Information: 4116 W 30TH ST 90016

Application / Permit
20016-30000-17295
Plan Check / Job No.
B20WL03071
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel (e) 1-story SFD, add an open sprial stair at rear of the bulding, re-frame (e) roof to add a rooftop deck, relocate kitchen, and add a bathroom.
Permit Issued
Issued on 10/16/2020
Issuing Office
Current Status
Permit Finaled on 11/6/2021

Permit Application Status History

Submitted 7/20/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 REZA HAGHIGHAT
Corrections Issued 8/13/2020 REZA HAGHIGHAT
Quality Review Completed 8/19/2020 TARIK SAOUD
Applicant returned to address corrections 9/23/2020 REZA HAGHIGHAT
Applicant returned to address corrections 10/1/2020 REZA HAGHIGHAT
Plan Check Approved 10/16/2020 REZA HAGHIGHAT
Issued 10/16/2020 APPLICANT
Building Plans Picked Up 10/19/2020 APPLICANT
Permit Finaled 11/5/2021 STUART CHAPMAN

Permit Application Clearance Information

Sewer availability Cleared 9/9/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/10/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Shokoufandeh,, Bahman; Lic. No.: C49709 13024 SKY VALLEY ROAD      LOS ANGELES, CA 90049

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2020 Corrections Issued STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 11/20/2020 Conditional Approval STUART CHAPMAN
Structural Steel Frame 1/27/2021 Partial Inspection DAVID FEILER
Wood Frame 1/27/2021 Corrections Issued DAVID FEILER
Wood Frame 3/4/2021 Partial Approval STUART CHAPMAN
Special/Order Compliance 3/18/2021 Corrections Issued STUART CHAPMAN
Special/Order Compliance 3/19/2021 Approved STUART CHAPMAN
Insulation 3/23/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/23/2021 Partial Approval STUART CHAPMAN
Drywall Nailing 4/6/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/6/2021 Partial Approval CHRISTOPHER DELLEFIELD
Special/Order Compliance 4/8/2021 Approved CHRISTOPHER DELLEFIELD
Final 10/26/2021 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 10/26/2021 Not Ready for Inspection STUART CHAPMAN
Final 11/5/2021 Permit Finaled STUART CHAPMAN
Smoke Detectors 11/5/2021 Approved STUART CHAPMAN