4332 W 60TH ST 90043

Certificate Information: 4332 W 60TH ST 90043

Application / Permit
20016-30000-17179
Plan Check / Job No.
B20WL03062
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached two-car garage to ADU
Permit Issued
Issued on 11/25/2020
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 8/17/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 8/25/2020 TARIK SAOUD
Plan Check Approved 11/18/2020 VLADIMIR ARUTYUNYAN
Issued 11/25/2020 APPLICANT
Building Plans Picked Up 12/1/2020 APPLICANT
CofO in Progress 9/16/2021 HORACE FULTZ
Permit Finaled 1/29/2022 DEROLD HAUFF
Permit Finaled 1/29/2022 DEROLD HAUFF
CofO Issued 1/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/4/2020 BARTON HOLMES
Address approval Cleared 9/25/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/25/2020 ELENA LOPEZ
Construction near power lines Cleared 10/14/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/21/2021 Off-Hour Fees Due
Underground Mechanical 1/21/2021 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 1/25/2021 No Access for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 2/4/2021 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 3/1/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 3/30/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 3/30/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 4/19/2021 Approved FREDDIE RIVERA
Wood Frame 4/19/2021 Approved FREDDIE RIVERA
HVAC-Rough 4/21/2021 Conditional Approval FREDDIE RIVERA
Insulation 4/21/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 4/21/2021 Corrections Issued FREDDIE RIVERA
Drywall Nailing 5/11/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 5/11/2021 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 5/18/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 7/9/2021 Approved FREDDIE RIVERA
Final 7/9/2021 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 7/9/2021 Approved FREDDIE RIVERA
Final 7/14/2021 OK to Issue CofO FREDDIE RIVERA
ELECTRICAL-Final 11/15/2021 Approved FREDDIE RIVERA