8931 S MANHATTAN PL 90047

Certificate Information: 8931 S MANHATTAN PL 90047

Application / Permit
20016-30000-17147
Plan Check / Job No.
B20WL03060
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage to ADU at rear of the lot.
Permit Issued
Issued on 10/24/2020
Issuing Office
Current Status
CofO Issued on 6/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 JAHANSHAH POURHASSAN
Corrections Issued 7/28/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 8/25/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 9/15/2020 JAHANSHAH POURHASSAN
Plan Check Approved 10/15/2020 JAHANSHAH POURHASSAN
Issued 10/24/2020 APPLICANT
Building Plans Picked Up 11/9/2020 APPLICANT
CofO in Progress 4/29/2021 FREDDIE RIVERA
Permit Finaled 6/25/2021 DEROLD HAUFF
Permit Finaled 6/25/2021 DEROLD HAUFF
CofO Issued 6/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/17/2020 MATTHEW CRAIG
Address approval Cleared 9/25/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/25/2020 WALLIE JONG
Sewer availability Cleared 9/25/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/20/2020 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 12/24/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 12/24/2020 Approved FREDDIE RIVERA
Insulation 12/24/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 12/24/2020 Partial Approval FREDDIE RIVERA
Pre-Inspection 12/24/2020 Corrections Issued FREDDIE RIVERA
Wood Frame 12/24/2020 Partial Approval FREDDIE RIVERA
Insulation 12/28/2020 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 12/28/2020 Approved EUGENE CASSIDY
Insulation 12/31/2020 Conditional Approval EUGENE CASSIDY
Insulation 1/5/2021 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Partial Approval FREDDIE RIVERA
HVAC-Rough 1/8/2021 Approved FREDDIE RIVERA
Drywall Nailing 1/12/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 2/10/2021 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 2/26/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/25/2021 Approved FREDDIE RIVERA
Final 3/25/2021 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 3/25/2021 Approved FREDDIE RIVERA
Final 4/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/3/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Final 4/14/2021 Not Ready for Inspection FREDDIE RIVERA
Final 4/29/2021 OK to Issue CofO FREDDIE RIVERA