4205-4207 N CANOGA DR 91364

Certificate Information: 4205-4207 N CANOGA DR 91364

Application / Permit
20016-30000-16296
Plan Check / Job No.
B20WL02938
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert(E) attached 2 car garage and portion of (E) SFD to ADU. PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Issued on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2020 APPLICANT
Assigned to Plan Check Engineer 7/21/2020 ALFREDO JARA
Corrections Issued 7/21/2020 ALFREDO JARA
Building Plans Picked Up 8/12/2020 APPLICANT
Applicant returned to address corrections 4/24/2021 ALFREDO JARA
Plan Check Approved 4/27/2021 ALFREDO JARA
Issued 5/11/2021 APPLICANT
CofO in Progress 12/1/2021 PETER FOLLING
CofO Issued 12/23/2021 MICHAEL SMITH
Permit Finaled 12/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/31/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/31/2020 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 7/31/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/31/2020 MARKOS PEREZ-BRAN
Grading Pre-Inspection Cleared 8/17/2020 BARTON HOLMES
Specific Plan Cleared 4/13/2021 LIZZI BEDUYA
Specific Plan Cleared 4/13/2021 LIZZI BEDUYA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/27/2021 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 6/14/2021 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 6/14/2021 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 6/14/2021 Approved PETER FOLLING
PLUMBING-Final 6/14/2021 Corrections Issued PETER FOLLING
BUILDING-Rough-Frame 6/24/2021 Corrections Issued PETER FOLLING
ELECTRICAL-Rough 6/24/2021 Approved PETER FOLLING
PLUMBING-Rough 6/24/2021 Approved PETER FOLLING
Interior/Exterior Lathing 6/30/2021 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 9/15/2021 Approved PETER FOLLING
Gas Test 9/15/2021 Approved PETER FOLLING
HVAC-Rough 9/15/2021 Approved PETER FOLLING
Insulation 9/22/2021 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Approved PETER FOLLING
Drywall Nailing 10/1/2021 Approved PETER FOLLING
Interior/Exterior Lathing 10/5/2021 Approved JAVIER RAMOS JR
Final 11/19/2021 Corrections Issued PETER FOLLING
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Approved PETER FOLLING
Smoke Detectors 11/19/2021 Approved PETER FOLLING
Final 11/30/2021 OK to Issue CofO PETER FOLLING