12602 W ROSE AVE 90066
Certificate Information: 12602 W ROSE AVE 90066
- Application / Permit
- 20016-30000-16089
- Plan Check / Job No.
- B20WL02897
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) garage to ADU per state law GCS 65852.2(e)(1)(A) at rear of the lot.
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 8/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | MANUEL GARCIA |
| Corrections Issued | 7/16/2020 | MANUEL GARCIA |
| Plan Check Approved | 12/9/2020 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 12/10/2020 | APPLICANT |
| Issued | 3/25/2021 | APPLICANT |
| CofO in Progress | 8/23/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 8/29/2023 | DANIEL ORRANTE |
| CofO Issued | 8/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/23/2020 | PATRICK MISCHLICH |
| Address approval | Cleared | 7/27/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/27/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2020 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 11/13/2020 | RIDWAN HARDY |
Contact Information
| Contractor | F S Design & Construction Inc; Lic. No.: 727272-B | 20520 OXNARD ST WOODLAND, CA 91367 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/6/2021 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/8/2021 | No Access for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/12/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/27/2021 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 4/27/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 4/29/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/29/2021 | Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 4/29/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 5/3/2021 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/3/2021 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 5/3/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Final | 8/2/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 8/2/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 9/20/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 9/20/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 4/4/2023 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/4/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 4/4/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Final | 8/7/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/7/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Final | 8/22/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | JESUS RODRIGUEZ |