12602 W ROSE AVE 90066

Certificate Information: 12602 W ROSE AVE 90066

Application / Permit
20016-30000-16089
Plan Check / Job No.
B20WL02897
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) garage to ADU per state law GCS 65852.2(e)(1)(A) at rear of the lot.
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 MANUEL GARCIA
Corrections Issued 7/16/2020 MANUEL GARCIA
Plan Check Approved 12/9/2020 JAHANSHAH POURHASSAN
Building Plans Picked Up 12/10/2020 APPLICANT
Issued 3/25/2021 APPLICANT
CofO in Progress 8/23/2023 JESUS RODRIGUEZ
Permit Finaled 8/29/2023 DANIEL ORRANTE
CofO Issued 8/29/2023 DANIEL ORRANTE
Permit Finaled 8/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/23/2020 PATRICK MISCHLICH
Address approval Cleared 7/27/2020 ANTHONY MAINEZ
Sewer availability Cleared 7/27/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/29/2020 ANTHONY MAINEZ
Construction near power lines Cleared 11/13/2020 RIDWAN HARDY

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B 20520 OXNARD ST      WOODLAND, CA 91367

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/6/2021 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 4/8/2021 No Access for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 4/12/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/27/2021 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 4/27/2021 Approved ENRIQUE MIRELES
Insulation 4/29/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/29/2021 Approved JESUS RODRIGUEZ
Pre-Inspection 4/29/2021 Partial Inspection SHAVONNE ESPINOZA
Drywall Nailing 5/3/2021 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 5/3/2021 Approved JESUS RODRIGUEZ
Special/Order Compliance 5/3/2021 Partial Inspection SHAVONNE ESPINOZA
Final 8/2/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 8/2/2022 Corrections Issued JESUS RODRIGUEZ
Final 9/20/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 9/20/2022 Corrections Issued JESUS RODRIGUEZ
Final 4/4/2023 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 4/4/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Not Ready JESUS RODRIGUEZ
Final 8/7/2023 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Not Ready JESUS RODRIGUEZ
Final 8/22/2023 OK to Issue CofO JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved JESUS RODRIGUEZ