1715 S BAGLEY AVE 90035
Certificate Information: 1715 S BAGLEY AVE 90035
- Application / Permit
- 20016-30000-15929
- Plan Check / Job No.
- B20WL02877
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage to accessory dwelling unit and storage per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/26/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2020 | JASON JANGADA |
| Building Plans Picked Up | 8/4/2020 | APPLICANT |
| Corrections Issued | 8/5/2020 | JASON JANGADA |
| Applicant returned to address corrections | 1/21/2021 | JASON JANGADA |
| Plan Check Approved | 2/9/2021 | ALFREDO JARA |
| Issued | 2/26/2021 | APPLICANT |
| CofO in Progress | 4/7/2022 | KEVIN SARGSYAN |
| Permit Finaled | 4/15/2022 | DANIEL ORRANTE |
| CofO Issued | 4/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/17/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/17/2020 | RIDWAN HARDY |
| Address approval | Cleared | 1/7/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/7/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | DINAH GARIN |
Contact Information
| Contractor | R B Construction; Lic. No.: 540333-B | 1473 CALLE VIOTETA THOUSAND OAKS, CA 91360 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/22/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/22/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/30/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 5/7/2021 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 5/7/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 5/7/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/7/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/11/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 5/11/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/11/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/17/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 5/17/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/17/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/17/2021 | Approved | KEVIN SARGSYAN |
| Insulation | 5/21/2021 | Approved | KEVIN SARGSYAN |
| Rough-Elec/Plmb/HVAC | 5/21/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 5/27/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 9/9/2021 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 9/9/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/8/2021 | Approved | KEVIN SARGSYAN |
| Final | 12/8/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 12/8/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 12/8/2021 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 3/22/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 4/7/2022 | OK to Issue CofO | KEVIN SARGSYAN |