3329 S PURDUE AVE 90066

Certificate Information: 3329 S PURDUE AVE 90066

Application / Permit
20016-30000-15921
Plan Check / Job No.
B20WL02872
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing 2-car garage into an accessory dwelling unit per state law GCS 65852.2(e)(1)(A). Construction per WFPP.
Permit Issued
Issued on 3/30/2021
Issuing Office
Current Status
CofO Issued on 1/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 KAVIAN REFAHI
Corrections Issued 7/20/2020 KAVIAN REFAHI
Applicant returned to address corrections 8/31/2020 PARISA ZAHABI
Applicant returned to address corrections 12/7/2020 MANUEL GARCIA
Building Plans Picked Up 1/15/2021 APPLICANT
Applicant returned to address corrections 2/9/2021 MANUEL GARCIA
Plan Check Approved 3/5/2021 JASON JANGADA
Issued 3/30/2021 APPLICANT
CofO in Progress 1/28/2022 KENNETH NAGLE
Permit Finaled 1/28/2022 KENNETH NAGLE
CofO Issued 1/28/2022 KENNETH NAGLE
Permit Finaled 1/28/2022 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 8/4/2020 DINAH GARIN
Sewer availability Cleared 8/4/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/7/2020 DINAH GARIN
Specific Plan Cleared 12/10/2020 PEDRO AYALA
Construction near power lines Cleared 1/19/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/20/2021 Corrections Issued EVAN COOPER
PLUMBING-Rough 4/20/2021 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/3/2021 Approved PIERRE VEGA
Sewer 7/14/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 7/21/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 8/5/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 8/5/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 8/5/2021 Approved OGANES TARAKHCHYAN
Wood Frame 8/5/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/18/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/20/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 8/23/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/24/2021 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 9/23/2021 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 10/19/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 12/20/2021 Approved JOHNNY MIRANDA
Final 12/20/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 12/20/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 12/20/2021 Approved JOHNNY MIRANDA
Final 1/14/2022 Conditional Approval JOHNNY MIRANDA