3178 S BENTLEY AVE 90034

Certificate Information: 3178 S BENTLEY AVE 90034

Application / Permit
20016-30000-15909
Plan Check / Job No.
B20WL02862
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel of (E) SFD to remove walls between kitchen/family room/den, enlarge opening at living room, reconfigure bathroom for access from the bedroom.
Permit Issued
Issued on 8/20/2020
Issuing Office
Current Status
Permit Finaled on 12/28/2020

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 JAHANSHAH POURHASSAN
Corrections Issued 7/10/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/28/2020 KAVIAN REFAHI
Plan Check Approved 8/5/2020 ALFREDO JARA
Issued 8/20/2020 APPLICANT
Building Plans Picked Up 8/28/2020 APPLICANT
Permit Finaled-Status Void 11/12/2020 OGANES TARAKHCHYAN
Re-Activate Permit 12/28/2020 OGANES TARAKHCHYAN
Permit Finaled 12/28/2020 KENNETH NAGLE

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Kellen,, David; Lic. No.: C15684 2701 AIRPORT AVE 202      SANTA MONICA, CA 90405
Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 8/31/2020 Partial Approval EVAN COOPER
Wood Frame 8/31/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 9/4/2020 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/4/2020 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/4/2020 Corrections Issued OGANES TARAKHCHYAN
MERV13>=Rough 9/4/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 9/4/2020 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 9/9/2020 Approved EVAN COOPER
Insulation 9/9/2020 Approved EVAN COOPER
PLUMBING-Rough 9/9/2020 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 9/18/2020 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/18/2020 Approved OGANES TARAKHCHYAN
Insulation 9/18/2020 Approved OGANES TARAKHCHYAN
MERV13>=Rough 9/18/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 9/18/2020 Approved OGANES TARAKHCHYAN
Drywall Nailing 9/28/2020 Approved KEVIN SARGSYAN
Shower Pan 9/29/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/14/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 11/12/2020 Approved OGANES TARAKHCHYAN
Final 11/12/2020 Conditional Approval OGANES TARAKHCHYAN
Gas Test 11/12/2020 Approved OGANES TARAKHCHYAN
HVAC-Final 11/12/2020 Approved OGANES TARAKHCHYAN
MERV13>=Final 11/12/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Final 11/12/2020 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/12/2020 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 11/12/2020 Approved OGANES TARAKHCHYAN
Final 12/28/2020 Permit Finaled KENNETH NAGLE
Service/Power Release 12/28/2020 Approved KENNETH NAGLE