11969 N ROSSITER PL 91342

Certificate Information: 11969 N ROSSITER PL 91342

Application / Permit
20016-30000-15881
Plan Check / Job No.
B20WL02849
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) PER WFPP
Permit Issued
Issued on 2/16/2021
Issuing Office
Current Status
CofO Issued on 8/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2020 APPLICANT
Assigned to Plan Check Engineer 7/9/2020 MARJAN SHENASI
Corrections Issued 7/13/2020 MARJAN SHENASI
Applicant returned to address corrections 1/11/2021 JASON JANGADA
Building Plans Picked Up 1/13/2021 APPLICANT
Plan Check Approved 2/4/2021 JASON JANGADA
Issued 2/16/2021 APPLICANT
CofO in Progress 8/16/2021 JENNIFER RABUCHIN
CofO Issued 8/16/2021 MICHAEL SMITH
Permit Finaled 8/16/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/4/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/4/2020 GABRIEL ROBLES
Sewer availability Cleared 8/4/2020 GABRIEL ROBLES
Construction near power lines Cleared 10/30/2020 RIDWAN HARDY
Grading Pre-Inspection Cleared 2/4/2021 MARJAN SHENASI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2021 Approved DANIEL ORRANTE
Underground Mechanical 6/16/2021 Approved DANIEL ORRANTE
BUILDING-Rough-Frame 6/22/2021 Corrections Issued JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 6/22/2021 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/23/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/23/2021 Approved JENNIFER RABUCHIN
Gas Test 6/23/2021 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 6/23/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/23/2021 Approved JENNIFER RABUCHIN
Insulation 6/25/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/28/2021 Partial Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 7/1/2021 Approved DEANDRE HOFFMAN
Drywall Nailing 7/7/2021 Approved JENNIFER RABUCHIN
Gas Test 7/7/2021 Partial Approval JENNIFER RABUCHIN
Service/Power Release 7/7/2021 Corrections Issued JENNIFER RABUCHIN
Sewer 7/7/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 7/7/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/14/2021 SGSOV Not Ready JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/21/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/21/2021 Corrections Issued MISAEL ESPARZA
Final 7/21/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 7/21/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 7/21/2021 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/21/2021 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 7/21/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 8/2/2021 Approved JENNIFER RABUCHIN
Final 8/2/2021 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 8/2/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/2/2021 Approved JENNIFER RABUCHIN
Smoke Detectors 8/2/2021 Approved JENNIFER RABUCHIN