6197 W TEMPLE HILL DR 90068
Certificate Information: 6197 W TEMPLE HILL DR 90068
- Application / Permit
- 20016-30000-14096
- Plan Check / Job No.
- B20WL02493
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel (e) master bathroom. relocate (e) powder room, remodel (2) existing bathrooms on 1st floor, remodel kitchen & living area, install pocket patio doors in living. remodel only no additional square footage
- Permit Issued
- Issued on 11/18/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/12/2021
Permit Application Status History
| Submitted | 6/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2020 | ALFREDO JARA |
| Corrections Issued | 6/18/2020 | ALFREDO JARA |
| Applicant returned to address corrections | 10/1/2020 | JASON JANGADA |
| Plan Check Approved | 11/12/2020 | RICHARD GARCIA |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| Issued | 11/18/2020 | APPLICANT |
| Permit Finaled | 11/10/2021 | BRIAN SULLIVAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/18/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | D C I Development Group Inc; Lic. No.: 1056455-B | 4569 VALLEY BLVD LOS ANGELES, CA 90032 |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/25/2020 | Corrections Issued | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 11/25/2020 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 11/25/2020 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/25/2020 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 11/25/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 11/25/2020 | Approved | SCOTT FINNILA |
| Wood Frame | 11/25/2020 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 12/2/2020 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 12/2/2020 | Approved | BRIAN SULLIVAN |
| Shower Pan | 12/2/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 12/2/2020 | Approved | BRIAN SULLIVAN |
| Insulation | 12/3/2020 | Approved | BRIAN SULLIVAN |
| Shower Pan | 12/3/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 12/9/2020 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 12/9/2020 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 1/5/2021 | Approved | BRIAN SULLIVAN |
| Final | 11/10/2021 | Permit Finaled | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 11/10/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 11/10/2021 | Approved | BRIAN SULLIVAN |