2539 S KELTON AVE 90064
Certificate Information: 2539 S KELTON AVE 90064
- Application / Permit
- 20016-30000-13395
- Plan Check / Job No.
- B20WL02365
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/2/2021
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2020 | RICARDO RAMIREZ |
| Corrections Issued | 6/9/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 8/31/2020 | PARISA ZAHABI |
| Plan Check Approved | 9/11/2020 | MANUEL GARCIA |
| Issued | 1/2/2021 | APPLICANT |
| Building Plans Picked Up | 1/12/2021 | APPLICANT |
| CofO in Progress | 2/16/2023 | KENNETH NAGLE |
| Permit Finaled | 2/16/2023 | DANIEL ORRANTE |
| CofO Issued | 2/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/9/2020 | RICARDO RAMIREZ |
| Construction within easement | Cleared | 7/11/2020 | WALTER RAMIREZ |
| Address approval | Cleared | 7/16/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/16/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 8/17/2020 | MATTHEW CRAIG |
| Distance to fire station | Cleared | 8/20/2020 | MATTHEW CRAIG |
Contact Information
| Architect | Swiers,, Donald Glen; Lic. No.: C11141 | 1930 PURDUE AVE #2 LOS ANGELES, CA 900257015 |
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/15/2021 | Corrections Issued | EVAN COOPER |
| Deputy Drilled-In Anchors | 3/18/2021 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/10/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/10/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Inspection | 6/2/2021 | Partial Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/27/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/27/2021 | Approved | KEVIN SARGSYAN |
| Wood Frame | 12/27/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/30/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 1/5/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Wood Frame | 1/5/2022 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/11/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Approved | CLAYTON GRAHAM |
| Wood Frame | 4/1/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/26/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 5/18/2022 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | JOHNNY MIRANDA |
| Final | 10/7/2022 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/7/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 10/7/2022 | Approved | JOHNNY MIRANDA |
| Final | 12/20/2022 | Conditional Approval | KENNETH NAGLE |