4269 S LYCEUM AVE 90066
Certificate Information: 4269 S LYCEUM AVE 90066
- Application / Permit
- 20016-30000-13187
- Plan Check / Job No.
- B20WL02329
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF GARAGE TO ADU
- Permit Issued
- Issued on 7/20/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2020 | TARIK SAOUD |
| Corrections Issued | 6/27/2020 | TARIK SAOUD |
| Quality Review Completed | 6/30/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 7/16/2020 | TARIK SAOUD |
| Issued | 7/20/2020 | APPLICANT |
| Building Plans Picked Up | 7/22/2020 | APPLICANT |
| CofO in Progress | 4/12/2021 | ENRIQUE MIRELES |
| CofO Issued | 5/3/2021 | VINCENT COTTON |
| Permit Finaled | 5/3/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/8/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2020 | DINAH GARIN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Bems Construction; Lic. No.: 1014009-B | 2930 E 5TH ST APT #8 LONG BEACH, CA 90814 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Reinforced Concrete Frame | 10/14/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/6/2020 | Partial Approval | ENRIQUE MIRELES |
| Sewer | 11/25/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/15/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/15/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/15/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/17/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 12/21/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/21/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 12/28/2020 | Approved | ENRIQUE MIRELES |
| Final | 3/19/2021 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/19/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/19/2021 | Approved | ENRIQUE MIRELES |
| Final | 3/30/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 4/12/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 4/12/2021 | Approved | ENRIQUE MIRELES |