750 N BEL-AIR ROAD 90077
Certificate Information: 750 N BEL-AIR ROAD 90077
- Application / Permit
- 20016-30000-13182
- Plan Check / Job No.
- B20WL02325
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR NON STRUCTURAL REMODEL OF SINGLE FAMILY DWELLING. FIRST FLOOR KITCHEN AREA AND SECOND FLOOR BEDROOM AREAS.
- Permit Issued
- Issued on 6/24/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/30/2022
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 6/15/2020 | RICARDO RAMIREZ |
| Issued | 6/24/2020 | APPLICANT |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Permit Finaled | 3/29/2022 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Hinkle,, Deanna Marie; Lic. No.: C35312 | 1014 TERI AVENUE TORRANCE, CA 90503 |
| Contractor | Mc Coy Peter Construction; Lic. No.: 493592-B | 9777 WILSHIRE BLVD #902 BEVERLY HILLS, CA 90212 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/24/2020 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/10/2020 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/10/2020 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 12/10/2020 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 12/10/2020 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/17/2020 | Partial Approval | MATT KELLERMAN |
| Insulation | 12/17/2020 | Partial Approval | MATT KELLERMAN |
| Light Gage Steel Frame | 12/17/2020 | Partial Approval | MATT KELLERMAN |
| Drywall Nailing | 12/23/2020 | Partial Approval | MATT KELLERMAN |
| Drywall Nailing | 12/28/2020 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Rough | 1/14/2021 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 2/4/2021 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 2/19/2021 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 2/19/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/12/2021 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/15/2021 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 4/1/2021 | Partial Approval | ANTHONY MCDOWALL |
| Insulation | 7/7/2021 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/15/2021 | Partial Approval | ADAM ESCOTO |
| Drywall Nailing | 7/23/2021 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Final | 9/21/2021 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Final | 10/14/2021 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 12/10/2021 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 2/23/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 2/23/2022 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 3/1/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 3/1/2022 | Approved | CHRISTOPHER WILSON |
| Final | 3/29/2022 | Permit Finaled | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 3/29/2022 | Approved | CHRISTOPHER WILSON |