2420 S WALNUT AVE 90291

Certificate Information: 2420 S WALNUT AVE 90291

Application / Permit
20016-30000-13155
Plan Check / Job No.
B20WL02314
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage to Accessory Dwelling Unit per state law GCS 65852.2(e)(1)(A).all work per engineering.
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
CofO Issued on 5/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2020 APPLICANT
Assigned to Plan Check Engineer 6/8/2020 MARJAN SHENASI
Corrections Issued 6/9/2020 MARJAN SHENASI
Applicant returned to address corrections 7/7/2020 MANUEL GARCIA
Applicant returned to address corrections 7/24/2020 PARISA ZAHABI
Applicant returned to address corrections 8/7/2020 JASON JANGADA
Applicant returned to address corrections 8/18/2020 RICHARD GARCIA
Plan Check Approved 8/31/2020 PARISA ZAHABI
Issued 9/24/2020 APPLICANT
Building Plans Picked Up 9/25/2020 APPLICANT
CofO in Progress 5/7/2021 ENRIQUE MIRELES
CofO Issued 5/21/2021 VINCENT COTTON
Permit Finaled 5/21/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 6/18/2020 DINAH GARIN
Sewer availability Cleared 6/18/2020 DINAH GARIN
Specific Plan Cleared 6/22/2020 VALERIA CEJA
Eng Process Fee Ord 176,300 Cleared 6/24/2020 DINAH GARIN

Contact Information

Contractor 3.1 Construction; Lic. No.: 1018269-B 14017 DUNROBIN AVE      BELLFLOWER, CA 90706
Engineer Chikhale,, Jonathan William; Lic. No.: C78893 2820 MILITARY AVENUE      LOS ANGELES, CA 90064

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/28/2020 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 9/28/2020 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 10/2/2020 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 10/2/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 11/6/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/6/2020 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 11/6/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/6/2020 Approved ENRIQUE MIRELES
Green Building Rough 11/6/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 11/6/2020 Approved ENRIQUE MIRELES
Wood Frame 11/6/2020 Approved ENRIQUE MIRELES
Insulation 11/12/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Approved ENRIQUE MIRELES
Drywall Nailing 11/17/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 12/3/2020 Approved ENRIQUE MIRELES
Shower Pan 12/3/2020 Approved ENRIQUE MIRELES
Gas Test 12/7/2020 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 12/7/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Final 3/12/2021 Approved ENRIQUE MIRELES
HVAC-Final 3/12/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 3/12/2021 Corrections Issued ENRIQUE MIRELES
Final 3/17/2021 Corrections Issued ENRIQUE MIRELES
Gas Test 3/17/2021 Approved ENRIQUE MIRELES
Green Building Final 3/17/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 3/17/2021 Approved ENRIQUE MIRELES
Final 5/7/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 5/7/2021 Approved ENRIQUE MIRELES