2998 N NICADA DR 90077

Certificate Information: 2998 N NICADA DR 90077

Application / Permit
20016-30000-12191
Plan Check / Job No.
B20WL02145
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel master bathroom and kitchen, extend kitchen into existing covered patio, add 6 windows, remove 1 window, replace 2 windows, replace 1 exterior door.
Permit Issued
Issued on 3/22/2021
Issuing Office
Current Status
Permit Finaled on 3/8/2022

Permit Application Status History

Submitted 5/21/2020 APPLICANT
Assigned to Plan Check Engineer 5/26/2020 RICARDO RAMIREZ
Corrections Issued 5/26/2020 RICARDO RAMIREZ
Applicant returned to address corrections 8/20/2020 MANUEL GARCIA
Applicant returned to address corrections 9/29/2020 ALFREDO JARA
Plan Check Approved 10/9/2020 ALFREDO JARA
Building Plans Picked Up 10/9/2020 APPLICANT
Issued 3/22/2021 APPLICANT
Permit Finaled 3/7/2022 GERMAN RODRIGUEZ MENDOZA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/9/2020 PATRICK MISCHLICH
Specific Plan Cleared 8/17/2020 TRACY WILLIAMS
ZI Cleared 8/17/2020 TRACY WILLIAMS
Miscellaneous Cleared 9/30/2020 HERMINIGILDO AGUSTIN

Contact Information

Architect Blumenberg,, Richard Leo; Lic. No.: C10862 15200 SUNSET BLVD STE 201      PACIFIC PALISADES, CA 90272
Contractor Construction By De Mill Inc; Lic. No.: 719903-B 543 COUNTRY CLUB DR STE B-609      SIMI VALLEY, CA 93065
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/10/2021 Partial Approval ANTHONY MCDOWALL
Underground Mechanical 6/17/2021 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 6/22/2021 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 7/6/2021 Partial Approval ANTHONY MCDOWALL
Rough-Elec/Plmb/HVAC 7/21/2021 Partial Approval CHRISTOPHER WILSON
Shower Pan 8/11/2021 Approved ANTHONY MCDOWALL
Insulation 8/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 8/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 8/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 8/23/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 8/26/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/30/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 9/14/2021 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 9/14/2021 Partial Approval JAVIER RAMOS JR
HVAC-Rough 9/14/2021 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 9/14/2021 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 10/7/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 10/7/2021 Approved JUAN VALENZUELA
Gas Test 10/7/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 10/7/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 10/7/2021 Approved JUAN VALENZUELA
Insulation 10/18/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 10/22/2021 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 10/29/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Not Ready GERMAN RODRIGUEZ MENDOZA
Final 2/28/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 2/28/2022 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 3/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Final 3/3/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Final 3/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 3/3/2022 Approved GERMAN RODRIGUEZ MENDOZA
Final 3/7/2022 Permit Finaled GERMAN RODRIGUEZ MENDOZA