6119-6121 N TOPEKA DR 91335
Certificate Information: 6119-6121 N TOPEKA DR 91335
- Application / Permit
- 20016-30000-12187
- Plan Check / Job No.
- B20WL02143
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) attached garage to ADU per ordinance.
- Permit Issued
- Issued on 9/1/2020
- Issuing Office
- Current Status
- CofO Corrected on 3/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2020 | RICARDO RAMIREZ |
| Corrections Issued | 5/27/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 7/16/2020 | PARISA ZAHABI |
| Plan Check Approved | 7/29/2020 | ALFREDO JARA |
| Building Plans Picked Up | 7/30/2020 | APPLICANT |
| Issued | 9/1/2020 | APPLICANT |
| CofO in Progress | 3/16/2021 | STEVEN BACK |
| CofO Issued-Status Void | 3/17/2021 | JOHN JANSON |
| Permit Finaled-Status Void | 3/17/2021 | JOHN JANSON |
| Re-Activate Permit | 3/18/2021 | JOHN JANSON |
| CofO Corrected | 3/26/2021 | JOHN JANSON |
| Permit Finaled | 3/26/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/5/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/5/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/5/2020 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 7/1/2020 | KURT CORRAL |
Contact Information
| Contractor | Y 9 Inc; Lic. No.: 903425-B | 11684 VENTURA BLVD #150 STUDIO CITY, CA 91604 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/8/2020 | Partial Approval | STEVEN BACK |
| Sewer | 9/8/2020 | Approved | STEVEN BACK |
| Deputy Drilled-In Anchors | 9/11/2020 | Approved | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/11/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 9/11/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 9/22/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/29/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 9/29/2020 | Approved | STEVEN BACK |
| Insulation | 9/29/2020 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 9/29/2020 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 10/2/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/2/2020 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 10/2/2020 | Approved | STEVEN BACK |
| Shower Pan | 10/2/2020 | Approved | STEVEN BACK |
| Insulation | 10/6/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/6/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 10/9/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 11/6/2020 | Corrections Issued | STEVEN BACK |
| Final | 11/6/2020 | Corrections Issued | STEVEN BACK |
| HVAC-Final | 11/6/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 11/6/2020 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/6/2020 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 11/6/2020 | Approved | STEVEN BACK |
| Final | 12/8/2020 | Corrections Issued | STEVEN BACK |
| Final | 12/21/2020 | Not Ready for Inspection | STEVEN BACK |
| Final | 1/12/2021 | No Access for Inspection | VINCENT HANLEY |
| Final | 3/16/2021 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 3/16/2021 | Approved | STEVEN BACK |