17 E NORTHSTAR ST 1-15 90292
Certificate Information: 17 E NORTHSTAR ST 1-15 90292
- Application / Permit
- 20016-30000-12079
- Plan Check / Job No.
- B20WL02130
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Convert (E) recreation room within apartment to ADU
- Permit Issued
- Issued on 10/3/2022
- Issuing Office
- Current Status
- Issued on 10/3/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 5/29/2020 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 8/31/2022 | JASON JANGADA |
| Plan Check Approved | 9/14/2022 | JASON JANGADA |
| Issued | 10/3/2022 | APPLICANT |
| Building Plans Picked Up | 10/12/2022 | APPLICANT |
| CofO in Progress | 5/8/2023 | FARHAD DADBIN |
| CofO in Progress | 5/8/2023 | FARHAD DADBIN |
| CofO Issued-Status Void | 5/10/2023 | DAVID TSAU |
| Permit Finaled-Status Void | 5/10/2023 | DAVID TSAU |
| Re-Activate Permit | 10/11/2023 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2022 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2022 | DENNIS BRAGIN |
| Coastal Zone | Cleared | 8/19/2022 | MAXFIELD VERMY |
| Specific Plan | Cleared | 8/19/2022 | MAXFIELD VERMY |
| ZA Case | Cleared | 8/19/2022 | MAXFIELD VERMY |
| ZA Case | Cleared | 8/19/2022 | MAXFIELD VERMY |
Contact Information
| Contractor | Canales Leonel; Lic. No.: 862131-B | 14920 OSWALD ST SYLMAR, CA 91342 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 1/4/2023 | Approved | GRANT WOODS |
| Wood Frame | 1/4/2023 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 1/18/2023 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 1/26/2023 | Approved | FARHAD DADBIN |
| Final | 4/19/2023 | Partial Inspection | SORIN CIRSTOIU |
| METHANE-Final | 4/19/2023 | Approved | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 4/19/2023 | Partial Inspection | SORIN CIRSTOIU |
| Final | 4/26/2023 | OK to Issue CofO | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2023 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 4/26/2023 | Approved | FARHAD DADBIN |