1444 1/2 S STEARNS DR 90035

Certificate Information: 1444 1/2 S STEARNS DR 90035

Application / Permit
20016-30000-11832
Plan Check / Job No.
B20WL02095
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION AND SECOND FLOOR ADDITION TO AN EXISTING GARAGE TO CREATE A NEW ADU
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
Issued on 3/23/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 PARISA ZAHABI
Corrections Issued 5/21/2020 PARISA ZAHABI
Building Plans Picked Up 5/22/2020 APPLICANT
Applicant returned to address corrections 10/5/2020 JASON JANGADA
Applicant returned to address corrections 12/17/2020 PARISA ZAHABI
Plan Check Approved 3/8/2021 TARIK SAOUD
Issued 3/23/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/13/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 10/13/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/14/2020 WALLIE JONG
Sewer availability Cleared 10/14/2020 WALLIE JONG
Construction near power lines Cleared 1/8/2021 RIDWAN HARDY

Contact Information

Contractor Great American Garage Conversions; Lic. No.: 773770-B 1140 SOUTH ALFRED STREET      LOS ANGELES, CA 90035
Engineer Gorbin,, James D; Lic. No.: S5859 210 S JUANITA AVE A      REDONDO BEACH, CA 90277

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 5/14/2021 Approved STUART CHAPMAN
Underground Mechanical 5/14/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/30/2021 Conditional Approval RUBEN SALAS
ELECTRICAL-Rough 7/30/2021 Approved RUBEN SALAS
HVAC-Rough 7/30/2021 Approved RUBEN SALAS
METHANE-Rough 7/30/2021 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 7/30/2021 Approved RUBEN SALAS
Special/Order Compliance 7/30/2021 Partial Inspection SHAVONNE ESPINOZA
BUILDING-Rough-Frame 8/11/2021 Conditional Approval FREDDIE RIVERA
METHANE-Rough 8/11/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 8/13/2021 Approved CALEB MEISTER
Insulation 8/17/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 8/17/2021 Not Ready for Inspection CALEB MEISTER
Drywall Nailing 8/25/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/25/2021 Approved STUART CHAPMAN
Shower Pan 8/25/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 12/8/2021 Approved JOSE AVILA
Final 12/8/2021 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved JOSE AVILA
Smoke Detectors 12/8/2021 Approved JOSE AVILA
ELECTRICAL-Final 12/13/2021 Approved JOSE AVILA
HVAC-Final 12/13/2021 Corrections Issued JOSE AVILA