1699 N FERRARI DR 90210
Certificate Information: 1699 N FERRARI DR 90210
- Application / Permit
- 20016-30000-11613
- Plan Check / Job No.
- B20WL02064
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO (E) SFD NO SQUARE FOOTAGE ADDED
- Permit Issued
- Issued on 9/24/2020
- Issuing Office
- Current Status
- Issued on 9/24/2020
Permit Application Status History
| Submitted | 6/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | ALFREDO JARA |
| Corrections Issued | 6/15/2020 | ALFREDO JARA |
| Applicant returned to address corrections | 7/9/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 8/4/2020 | MANUEL GARCIA |
| Plan Check Approved | 9/14/2020 | ALFREDO JARA |
| Issued | 9/24/2020 | APPLICANT |
| Building Plans Picked Up | 9/28/2020 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 6/29/2020 | JASON SHEETS |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 7/28/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 9/3/2020 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 9/26/2020 | Partial Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/16/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 10/23/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Steel/Welding | 11/17/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2021 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 3/8/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Corrections Issued | ANTHONY MCDOWALL |
| HVAC-Rough | 3/19/2021 | Conditional Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 3/19/2021 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 4/19/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 4/19/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 4/23/2021 | Partial Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 4/30/2021 | Approved | ANTHONY MCDOWALL |
| HVAC-Rough | 5/4/2021 | Approved | ANTHONY MCDOWALL |
| Light Gage Steel Frame | 5/14/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Wood Frame | 5/14/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Insulation | 6/18/2021 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 6/30/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Drywall Nailing | 8/6/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 10/4/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 10/12/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 10/15/2021 | Approved | DEANDRE HOFFMAN |
| Shower Pan | 10/15/2021 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 9/7/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 9/13/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 9/13/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 9/19/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 9/19/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 9/21/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 9/21/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 9/21/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 9/21/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 12/13/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |