8351 S WESTLAWN AVE 90045
Certificate Information: 8351 S WESTLAWN AVE 90045
- Application / Permit
- 20016-30000-11296
- Plan Check / Job No.
- B20WL02034
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Garage conversion to an ADU per ordinance
- Permit Issued
- Issued on 7/10/2020
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | REZA HAGHIGHAT |
| Corrections Issued | 6/8/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 6/16/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/6/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 7/10/2020 | REZA HAGHIGHAT |
| Issued | 7/10/2020 | APPLICANT |
| Building Plans Picked Up | 7/13/2020 | APPLICANT |
| CofO in Progress | 9/15/2021 | BRENDAN LOONEY |
| Permit Finaled | 9/25/2021 | DANIEL ORRANTE |
| CofO Issued | 9/25/2021 | DANIEL ORRANTE |
| Permit Finaled | 9/25/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2020 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 7/1/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/1/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 7/7/2020 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2020 | ANTHONY MAINEZ |
Contact Information
| Contractor | Tran Bao; Lic. No.: 849538-B | 2521 W AVENUE 31 LOS ANGELES, CA 90065 |
| Engineer | Brunmier,, David Wayne; Lic. No.: C80545 | 18567 VALLEY BLVD. BLOOMINGTON, CA 92316 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 7/15/2020 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/15/2020 | Approved | JUAN VALENZUELA |
| Sewer | 10/1/2020 | Approved | JOHNNY MIRANDA |
| Pre-Inspection | 2/16/2021 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 3/19/2021 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 6/14/2021 | Approved | RICHARD ROBLES |
| Gas Test | 6/14/2021 | Approved | RICHARD ROBLES |
| Green Building Rough | 6/14/2021 | Corrections Issued | RICHARD ROBLES |
| Rough-Elec/Plmb/HVAC | 6/14/2021 | Corrections Issued | RICHARD ROBLES |
| ELECTRICAL-Rough | 6/18/2021 | Approved | ANTHONY MCDOWALL |
| Insulation | 6/23/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Insulation | 6/30/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/30/2021 | Approved | AMY COLIN |
| Shower Pan | 6/30/2021 | Approved | AMY COLIN |
| Drywall Nailing | 7/12/2021 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/30/2021 | Approved | BRENDAN LOONEY |
| Final | 8/30/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 8/30/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 8/30/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 8/30/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 8/30/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 9/9/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 9/9/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 9/9/2021 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 9/9/2021 | Approved | BRENDAN LOONEY |
| Final | 9/10/2021 | OK to Issue CofO | BRENDAN LOONEY |