2049 N BALMER DR 90039
Certificate Information: 2049 N BALMER DR 90039
- Application / Permit
- 20016-30000-11108
- Plan Check / Job No.
- B20WL02003
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (E) UNDERFLOOR AREA (MUD ROOM & 138 SF STORAGE) CONVERSION TO (N) BATHROOM AND BEDROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 5/14/2020 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 6/10/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/22/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/9/2020 | ALFREDO JARA |
| Plan Check Approved | 7/29/2020 | PARISA ZAHABI |
| Issued | 8/19/2020 | APPLICANT |
| Building Plans Picked Up | 9/8/2020 | APPLICANT |
| CofO in Progress | 10/9/2020 | ARTHUR SARGSYAN |
| CofO in Progress | 10/9/2020 | ARTHUR SARGSYAN |
| Permit Finaled | 10/21/2020 | DEROLD HAUFF |
| CofO Issued | 10/21/2020 | DEROLD HAUFF |
| Permit Finaled | 10/21/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/2/2020 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/2/2020 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 9/2/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 9/2/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/2/2020 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 9/2/2020 | Approved | JOSEPH MCGARRY |
| Shower Pan | 9/2/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/9/2020 | Approved | JOSEPH MCGARRY |
| Insulation | 9/9/2020 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/9/2020 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 9/9/2020 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 9/16/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 10/1/2020 | Corrections Issued | DONALD CRICHLOW |
| Final | 10/1/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| HVAC-Final | 10/1/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| PLUMBING-Final | 10/1/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| SGSOV-Seismic Gas S/O Valve | 10/1/2020 | SGSOV Approved | DONALD CRICHLOW |
| Smoke Detectors | 10/1/2020 | Partial Approval | DONALD CRICHLOW |
| Final | 10/8/2020 | OK to Issue CofO | ARTHUR SARGSYAN |
| Smoke Detectors | 10/8/2020 | Approved | ARTHUR SARGSYAN |