5929 3/4 S FIGUEROA ST 90003
Certificate Information: 5929 3/4 S FIGUEROA ST 90003
- Application / Permit
- 20016-30000-10793
- Plan Check / Job No.
- B20WL01962
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) Detached garage into ADU and Addition to ADU . PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 3/4/2022
- Issuing Office
- Current Status
- CofO Issued on 3/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | ALFREDO JARA |
| Corrections Issued | 5/27/2020 | ALFREDO JARA |
| Quality Review Completed | 6/5/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 6/12/2020 | APPLICANT |
| Applicant returned to address corrections | 1/19/2021 | ALFREDO JARA |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| Applicant returned to address corrections | 2/18/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 6/8/2021 | ALFREDO JARA |
| Plan Check Approved | 10/18/2021 | ALFREDO JARA |
| Issued | 3/4/2022 | APPLICANT |
| Permit Finaled | 3/26/2024 | WINSTON DUNNING |
| CofO Issued | 3/26/2024 | WINSTON DUNNING |
| Permit Finaled | 3/26/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/21/2020 | MICHAEL GREGERSON |
| Miscellaneous | Cleared | 9/24/2020 | AIDA KARAPETIAN |
| Address approval | Cleared | 9/25/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/25/2020 | JEANIE LAM |
| Sewer availability | Cleared | 9/25/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2020 | JEANIE LAM |
| CPC | Cleared | 10/20/2020 | SARAHI ORTEGA |
| Community Plan Implem. Overlay | Cleared | 10/26/2020 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 11/6/2020 | DAVID URITA |
| Green Code | Cleared | 1/19/2021 | ALFREDO JARA |
| Hydrant and Access approval | Cleared | 9/27/2021 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/30/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Excavation/Setback/Form/Re-Bar | 4/20/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 4/21/2022 | Conditional Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 5/18/2022 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 6/7/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 6/7/2022 | Corrections Issued | RUSSELL BONVOULOIR |
| Insulation | 1/27/2023 | Corrections Issued | ALAN MORELOS |
| Drywall Nailing | 3/31/2023 | Approved | ALAN MORELOS |
| Green Building Rough | 3/31/2023 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 3/31/2023 | Partial Approval | ALAN MORELOS |
| Interior/Exterior Lathing | 4/5/2023 | Approved | ALAN MORELOS |
| Final | 10/26/2023 | Corrections Issued | DARRYL ARNOLD |
| Green Building Final | 10/26/2023 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/26/2023 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/26/2023 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/26/2024 | Conditional Approval | WINSTON DUNNING |
| Green Building Final | 3/26/2024 | Approved | WINSTON DUNNING |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | WINSTON DUNNING |
| Smoke Detectors | 3/26/2024 | Approved | WINSTON DUNNING |
| Wood Frame | 3/26/2024 | Approved | WINSTON DUNNING |