3750 S 2ND AVE 90018

Certificate Information: 3750 S 2ND AVE 90018

Application / Permit
20016-30000-10606
Plan Check / Job No.
B20WL01918
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRE DAMAGE REPAIR TO SINGLE FAMILY DWELLING. STRUCTURE IS LESS THAN SUBSTANTIALLY STRUCTURALLY DAMAGED DUE TO FIRE. REMOVE OR REINFORCE DAMAGED ROOF FRAMING MEMBERS. REMOVE AND REPAIR EXTERIOR FIRE DAMAGED FINISHES TO MATCH EXISTING. NO CHANGES TO BUILDING DIMENSIONS OR USE.
Permit Issued
Issued on 3/29/2021
Issuing Office
Current Status
Permit Finaled on 8/31/2022

Permit Application Status History

Submitted 4/30/2020 APPLICANT
Assigned to Plan Check Engineer 5/1/2020 RICARDO RAMIREZ
Corrections Issued 5/1/2020 RICARDO RAMIREZ
Plan Check Approved 2/23/2021 KAVIAN REFAHI
Building Plans Picked Up 2/26/2021 APPLICANT
Issued 3/29/2021 APPLICANT
Permit Finaled 8/30/2022 STUART CHAPMAN

Permit Application Clearance Information

HPOZ Cleared 2/4/2021 MAX LODER
Historic monument Cleared 2/4/2021 MAX LODER
ZI Cleared 2/4/2021 MAX LODER

Contact Information

Contractor Whitehouse Builders; Lic. No.: 956410-B 28130 AVE CROCKER #304      VALENCIA, CA 91355
Engineer Youn,, Hai; Lic. No.: C84250 3463 OCEAN VIEW BLVD      GLENDALE, CA 91208

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/18/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Partial Approval STUART CHAPMAN
Rough-Elec/Plmb/HVAC 8/18/2021 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 12/14/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 12/14/2021 Partial Approval STUART CHAPMAN
Rough-Elec/Plmb/HVAC 12/14/2021 Approved STUART CHAPMAN
Insulation 12/20/2021 Not Ready for Inspection AMY COLIN
Insulation 12/21/2021 Approved STUART CHAPMAN
Drywall Nailing 1/5/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 8/30/2022 Approved STUART CHAPMAN
Final 8/30/2022 Permit Finaled STUART CHAPMAN
HVAC-Final 8/30/2022 Approved STUART CHAPMAN
PLUMBING-Final 8/30/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 8/30/2022 Approved STUART CHAPMAN