1518 N BLUE JAY WAY 90069

Certificate Information: 1518 N BLUE JAY WAY 90069

Application / Permit
20016-30000-10259
Plan Check / Job No.
B20WL01849
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
Addition to (e) pool house
Permit Issued
Issued on 7/6/2021
Issuing Office
Current Status
CofO Issued on 8/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 5/27/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 6/5/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/12/2020 VLADIMIR ARUTYUNYAN
Applicant returned to address corrections 5/18/2021 REZA HAGHIGHAT
Plan Check Approved 6/28/2021 VLADIMIR ARUTYUNYAN
Issued 7/6/2021 APPLICANT
Building Plans Picked Up 7/7/2021 APPLICANT
CofO in Progress 7/12/2024 RAUL BARAJAS
Permit Finaled 8/21/2024 RONALD MYRICK
CofO Issued 8/21/2024 RONALD MYRICK
Permit Finaled 8/21/2024 RONALD MYRICK

Permit Application Clearance Information

Green Code Cleared 11/17/2020 RICHARD GARCIA
Low Impact Development Cleared 4/14/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/23/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/13/2021 THOMAS LANG
GPI Written Notices Cleared 5/18/2021 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 5/18/2021 REZA HAGHIGHAT
BHO/Hillside ordinance Cleared 5/19/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 5/19/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 5/19/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 5/19/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 5/19/2021 WALLIE JONG

Contact Information

Contractor Bar Design And Construction Inc; Lic. No.: 786816-B 11009 1/2 HESBY ST      NORTH HOLLYWOOD, CA 91601

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/30/2021 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Approved RAUL BARAJAS
HVAC-Rough 1/13/2022 Approved RAUL BARAJAS
ELECTRICAL-Rough 1/14/2022 Approved RAUL BARAJAS
PLUMBING-Rough 2/2/2022 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 5/5/2022 Not Ready for Inspection RUBEN SALAS
Green Building Rough 5/5/2022 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 6/9/2022 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 6/9/2022 Approved RAUL BARAJAS
Green Building Rough 6/9/2022 Approved RAUL BARAJAS
Pool Piping 6/13/2022 Not Ready for Inspection RAUL BARAJAS
Pool/Spa Cover 6/13/2022 Not Ready for Inspection RAUL BARAJAS
Sewer 6/21/2022 Partial Approval ADAM ESCOTO
Interior/Exterior Lathing 9/8/2022 Partial Approval RYAN SALAZAR
Insulation 9/30/2022 Not Ready for Inspection RAUL BARAJAS
Insulation 10/4/2022 Approved RAUL BARAJAS
Drywall Nailing 1/26/2023 Approved RAUL BARAJAS
BUILDING-Rough-Frame 1/9/2024 Approved STUART CHAPMAN
Final 1/9/2024 Corrections Issued STUART CHAPMAN
Green Building Final 1/9/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 1/9/2024 SGSOV Approved STUART CHAPMAN
Smoke Detectors 1/9/2024 Approved STUART CHAPMAN
Final 5/6/2024 Not Ready for Inspection RAUL BARAJAS
Final 5/21/2024 Corrections Issued RAUL BARAJAS
Final 7/2/2024 Corrections Issued RAUL BARAJAS
Final 7/11/2024 OK to Issue CofO RAUL BARAJAS