2021 N CUMMINGS DR 90027
Certificate Information: 2021 N CUMMINGS DR 90027
- Application / Permit
- 20016-30000-10237
- Plan Check / Job No.
- B20WL01842
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Inerior remodel, 2-story SFR. Remodel kitchen, bathrooms, and bedrooms.
- Permit Issued
- Issued on 10/30/2020
- Issuing Office
- Current Status
- Permit Finaled on 1/18/2023
Permit Application Status History
| Submitted | 4/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2020 | JASON JANGADA |
| Corrections Issued | 4/30/2020 | JASON JANGADA |
| Plan Check Approved | 10/20/2020 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 10/21/2020 | APPLICANT |
| Issued | 10/30/2020 | APPLICANT |
| Permit Finaled | 1/17/2023 | JOAQUIN GREENOUGH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/9/2020 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/19/2021 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/2/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/17/2021 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 8/6/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/31/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 8/31/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 8/31/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 9/14/2021 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/24/2021 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/30/2021 | No Access for Inspection | SCOTT FINNILA |
| HVAC-Rough | 9/30/2021 | No Access for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/1/2021 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 10/1/2021 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/14/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Special/Order Compliance | 10/14/2021 | Approved | HECTOR ALIKHAN |
| Deputy Drilled-In Anchors | 10/19/2021 | Conditional Approval | ROBERT CORNELL |
| BUILDING-Rough-Frame | 10/21/2021 | Partial Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 10/27/2021 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 11/16/2021 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/16/2021 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 11/16/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 11/22/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 11/22/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 11/22/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/9/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 12/9/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Final | 12/9/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 12/9/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 12/9/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 1/17/2023 | Permit Finaled | JOAQUIN GREENOUGH |