1244 N MORAGA DR 90049

Certificate Information: 1244 N MORAGA DR 90049

Application / Permit
20016-30000-09567
Plan Check / Job No.
B20WL01723
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO INTERIOR AND EXTERIOR OF EXISTING TWO STORY SINGLE FAMILY DWELING WITH ATTACHED GARAGE.
Permit Issued
Issued on 6/10/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 3/13/2022

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 4/29/2020 RICARDO RAMIREZ
Corrections Issued 4/29/2020 RICARDO RAMIREZ
Plan Check Approved 5/28/2020 RICARDO RAMIREZ
Issued 6/10/2020 LADBS
Building Plans Picked Up 6/10/2020 APPLICANT
Permit Finaled 3/11/2022 CARLOS MATAMOROS

Permit Application Clearance Information

Miscellaneous Cleared 5/5/2020 MAXFIELD VERMY
Miscellaneous Cleared 5/5/2020 MAXFIELD VERMY
ZA Case Cleared 5/5/2020 MAXFIELD VERMY
Grading Pre-Inspection Cleared 5/28/2020 RICARDO RAMIREZ

Contact Information

Architect Manion,, Richard M; Lic. No.: C26957 11400 WEST OLYMPIC BLVD SUITE 410      LOS ANGELES, CA 90025
Contractor J R C Group Inc; Lic. No.: 980658-B 8981 SUNSET BLVD STE 505      LOS ANGELES, CA 90069
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/7/2020 Corrections Issued CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 10/14/2020 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 10/20/2020 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 12/24/2020 Partial Approval CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 12/24/2020 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 1/13/2021 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 1/13/2021 Partial Approval CARLOS MATAMOROS
HVAC-Rough 1/13/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 1/13/2021 Partial Approval CARLOS MATAMOROS
Insulation 1/20/2021 Not Ready for Inspection CARLOS MATAMOROS
Shower Pan 1/20/2021 Not Ready for Inspection CARLOS MATAMOROS
Insulation 1/22/2021 Partial Approval CARLOS MATAMOROS
Shower Pan 1/22/2021 Partial Approval CARLOS MATAMOROS
Drywall Nailing 2/3/2021 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/3/2021 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 2/9/2021 Partial Approval CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 2/9/2021 Partial Approval CARLOS MATAMOROS
Drywall Nailing 2/12/2021 Partial Approval CARLOS MATAMOROS
Insulation 2/12/2021 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 2/12/2021 Approved CARLOS MATAMOROS
Shower Pan 2/12/2021 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 2/18/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/22/2021 Not Ready for Inspection CARLOS MATAMOROS
Shower Pan 2/22/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/2/2021 Approved CARLOS MATAMOROS
Drywall Nailing 3/10/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/10/2021 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 3/12/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 3/12/2021 Approved CARLOS MATAMOROS
Green Building Rough 3/12/2021 Approved CARLOS MATAMOROS
HVAC-Rough 3/12/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/12/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/12/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 11/4/2021 Not Ready for Inspection CARLOS MATAMOROS
Final 11/4/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 11/4/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 11/4/2021 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 11/4/2021 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Not Ready CARLOS MATAMOROS
Final 1/19/2022 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/19/2022 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 1/19/2022 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 3/4/2022 Not Ready for Inspection CARLOS MATAMOROS
Final 3/4/2022 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 3/4/2022 Partial Approval CARLOS MATAMOROS
PLUMBING-Final 3/4/2022 Partial Approval CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 3/4/2022 Corrections Issued CARLOS MATAMOROS
Final 3/11/2022 Permit Finaled CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 3/11/2022 Approved CARLOS MATAMOROS