- CONVERSION OF 26'-1"X 20'-0" (E) GARAGE TO ADU PER GCS 65852.2(e)(1)(A). NO SF ADDED
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2020 | PARISA ZAHABI |
| Corrections Issued | 5/11/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 7/24/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 9/11/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 10/16/2020 | PARISA ZAHABI |
| Plan Check Approved | 12/1/2020 | KAVIAN REFAHI |
| Issued | 12/21/2020 | APPLICANT |
| Building Plans Picked Up | 12/22/2020 | APPLICANT |
| CofO in Progress | 9/15/2021 | KEVIN SARGSYAN |
| Permit Finaled | 12/20/2021 | DANIEL ORRANTE |
| CofO Issued | 12/20/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/20/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/12/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2020 | DINAH GARIN |
| Construction near power lines | Cleared | 7/6/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 9/11/2020 | PARISA ZAHABI |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/12/2021 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Inspection | 1/19/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 2/2/2021 | No Result Entered | RONALD WEBER |
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/3/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/8/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/8/2021 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/11/2021 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 2/11/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 2/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Rough | 2/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 2/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 3/12/2021 | No Result Entered | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Insulation | 3/15/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Rough | 3/15/2021 | Approved | KEVIN SARGSYAN |
| Wood Frame | 3/15/2021 | Partial Approval | KEVIN SARGSYAN |
| Drywall Nailing | 3/22/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 3/22/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 3/22/2021 | Partial Approval | KEVIN SARGSYAN |
| Wood Frame | 3/22/2021 | Approved | KEVIN SARGSYAN |
| Final | 8/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 8/20/2021 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 8/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| Final | 9/14/2021 | Conditional Approval | KEVIN SARGSYAN |