327 N LAS PALMAS AVE 90004

Certificate Information: 327 N LAS PALMAS AVE 90004

Application / Permit
20016-30000-08350
Plan Check / Job No.
B20WL01437
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing Garage to ADU per ordiance.
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
CofO Issued on 5/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 MANUEL GARCIA
Corrections Issued 5/13/2020 MANUEL GARCIA
Quality Review Completed 5/19/2020 TARIK SAOUD
Green Plans Picked Up 6/18/2020 APPLICANT
Applicant returned to address corrections 6/30/2020 MANUEL GARCIA
Applicant returned to address corrections 7/15/2020 MANUEL GARCIA
Plan Check Approved 8/20/2020 MANUEL GARCIA
Issued 9/11/2020 APPLICANT
Building Plans Picked Up 9/18/2020 APPLICANT
CofO in Progress 5/4/2021 CHRIS CHRISTENSEN
Permit Finaled 5/8/2021 DEROLD HAUFF
CofO Issued 5/8/2021 DEROLD HAUFF
Permit Finaled 5/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/15/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 5/15/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/15/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/19/2020 HISASHI KOBAYAKAWA
HPOZ Cleared 7/16/2020 SUKI GERSHENHORN
ZI Cleared 7/16/2020 SUKI GERSHENHORN
Green Code Cleared 8/20/2020 MANUEL GARCIA

Contact Information

Contractor Charles Latham Construction; Lic. No.: 580175-B 22916 ELKWOOD STREET      WEST HILLS, CA 91304

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/22/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 10/29/2020 Not Ready for Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Partial Approval JOSEPH MCGARRY
Green Building Rough 12/22/2020 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 12/22/2020 Corrections Issued JOSEPH MCGARRY
Green Building Rough 1/8/2021 Not Ready for Inspection ROBERT VORHIS
METHANE-Rough 1/8/2021 Approved ROBERT VORHIS
Wood Frame 1/8/2021 Not Ready for Inspection ROBERT VORHIS
Deputy Drilled-In Anchors 1/15/2021 No Access for Inspection ELMER BLAND
Green Building Rough 1/25/2021 Corrections Issued CHRIS CHRISTENSEN
Wood Frame 1/25/2021 Conditional Approval CHRIS CHRISTENSEN
Drywall Nailing 2/10/2021 Approved CHRIS CHRISTENSEN
Insulation 2/10/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/11/2021 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/8/2021 Approved CHRIS CHRISTENSEN
Final 4/14/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 4/14/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 4/14/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/14/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 4/14/2021 Approved CHRIS CHRISTENSEN
Wood Frame 4/14/2021 Approved CHRIS CHRISTENSEN
Final 4/30/2021 OK to Issue CofO CHRIS CHRISTENSEN