13051 W VENICE BLVD 90066
Certificate Information: 13051 W VENICE BLVD 90066
- Application / Permit
- 20016-30000-08284
- Plan Check / Job No.
- B20WL01423
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMODEL TO EXISTING 2-STORY DUPLEX. NEW WINDOW, AND EXTERIOR GUARDRAIL/HANDRAIL.
- Permit Issued
- Issued on 6/2/2020
- Issuing Office
- Current Status
- Permit Finaled on 10/26/2020
Permit Application Status History
| Submitted | 4/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | SERGIO SILVA |
| Corrections Issued | 4/22/2020 | SERGIO SILVA |
| Quality Review Completed | 5/1/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/14/2020 | SERGIO SILVA |
| Green Plans Picked Up | 5/22/2020 | APPLICANT |
| Plan Check Approved | 5/28/2020 | SERGIO SILVA |
| Building Plans Picked Up | 5/28/2020 | APPLICANT |
| Issued | 6/2/2020 | APPLICANT |
| Permit Finaled | 10/26/2020 | ENRIQUE MIRELES |
Permit Application Clearance Information
| Permit | Cleared | 4/24/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/24/2020 | DINAH GARIN |
| "Q" conditions | Cleared | 4/30/2020 | DENZEL HENDERSON |
| Specific Plan | Cleared | 4/30/2020 | DENZEL HENDERSON |
| ZI | Cleared | 4/30/2020 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2020 | DINAH GARIN |
| Sewer availability | Cleared | 5/1/2020 | DINAH GARIN |
| Specific Plan | Cleared | 5/4/2020 | PEDRO AYALA |
| Grading Pre-Inspection | Cleared | 5/15/2020 | VASIL MIHALEV |
| GPI Written Notices | Cleared | 5/22/2020 | SERGIO SILVA |
Contact Information
| Contractor | First Max Harrison; Lic. No.: 1060902-B | 4459 S CENTINELA AVENUE LOS ANGELES, CA 90066 |
| Engineer | Katsuyama,, Julie Christine; Lic. No.: C86425 | 5 CHARLEMONT DR ALISO VIEJO, CA 92656 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/8/2020 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 6/8/2020 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 6/11/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/11/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/16/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/16/2020 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 6/16/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 6/16/2020 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/18/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/18/2020 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 6/18/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/18/2020 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/19/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/19/2020 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 6/19/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/19/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Shower Pan | 6/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Wood Frame | 6/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/24/2020 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 6/24/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 6/25/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/29/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 6/29/2020 | Approved | EVAN COOPER |
| Green Building Rough | 6/29/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/29/2020 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 7/2/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/7/2020 | Approved | JUAN VALENZUELA |
| Gas Test | 10/9/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 10/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 10/9/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/14/2020 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 10/14/2020 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 10/14/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Service/Power Release | 10/14/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 10/22/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 10/22/2020 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 10/22/2020 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 10/22/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/26/2020 | Approved | ENRIQUE MIRELES |
| Final | 10/26/2020 | Permit Finaled | ENRIQUE MIRELES |
| HVAC-Final | 10/26/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 10/26/2020 | Approved | ENRIQUE MIRELES |