1213 N RIMMER AVE 90272
Certificate Information: 1213 N RIMMER AVE 90272
- Application / Permit
- 20016-30000-08012
- Plan Check / Job No.
- B20WL01398
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- COVERED PATIO ADDITION TO REAR OF THE HOUSE. KITCHEN REMODEL, 3 BATHROOM AND LAUNDRY AND NEW GARAGE DOOR. PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Current Status
- CofO Issued on 4/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2020 | PARISA ZAHABI |
| Corrections Issued | 3/23/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 4/27/2020 | KAVIAN REFAHI |
| Plan Check Approved | 5/18/2020 | ALFREDO JARA |
| Issued | 5/27/2020 | APPLICANT |
| Building Plans Picked Up | 5/29/2020 | APPLICANT |
| CofO in Progress | 4/1/2022 | JOHN KIDWELL |
| Permit Finaled | 4/20/2022 | DANIEL ORRANTE |
| CofO Issued | 4/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 5/15/2020 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 5/18/2020 | KAVIAN REFAHI |
Contact Information
| Contractor | Ricard Glenn Construction Inc; Lic. No.: 523293-B | 438 ALMAR AVENUE PACIFIC PALISADES, CA 90272 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/10/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/30/2020 | Approved | JOHN KIDWELL |
| HVAC-Rough | 6/30/2020 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 7/14/2020 | Approved | JOHN KIDWELL |
| Wood Frame | 7/14/2020 | Approved | JOHN KIDWELL |
| Drywall Nailing | 7/31/2020 | Approved | ROBERT SHELLY |
| Interior/Exterior Lathing | 7/31/2020 | Approved | ROBERT SHELLY |
| Footing/Foundation/Slab | 8/12/2020 | Approved | ROBERT SHELLY |
| Wood Frame | 9/22/2020 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 10/14/2020 | Corrections Issued | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/26/2020 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/26/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 10/26/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Gas Test | 1/14/2021 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/18/2021 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | JOHN KIDWELL |
| Final | 1/24/2022 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 1/24/2022 | Approved | JOHN KIDWELL |
| Green Building Rough | 1/24/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 1/24/2022 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 1/24/2022 | Approved | JOHN KIDWELL |
| Final | 3/31/2022 | OK to Issue CofO | JOHN KIDWELL |