1226 S ST ANDREWS PL 90019
Certificate Information: 1226 S ST ANDREWS PL 90019
- Application / Permit
- 20016-30000-07963
- Plan Check / Job No.
- B20WL01392
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- interior remodeling, (n) bathroom at (e) attic (convert attic to bathroom); no exterior work
- Permit Issued
- Issued on 10/1/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2020 | KAVIAN REFAHI |
| Corrections Issued | 3/24/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/10/2020 | SINA KHOSRAVI |
| Plan Check Approved | 9/11/2020 | SINA KHOSRAVI |
| Building Plans Picked Up | 9/15/2020 | APPLICANT |
| Issued | 10/1/2020 | APPLICANT |
| CofO in Progress | 3/5/2024 | SCOTT FINNILA |
| Permit Finaled | 3/30/2025 | DEROLD HAUFF |
| CofO Issued | 3/30/2025 | DEROLD HAUFF |
| Permit Finaled | 3/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 9/3/2020 | AMANDA KAINER |
Contact Information
| Contractor | Composition Construction Inc; Lic. No.: 1000496-B | 1705 BARNARD DRIVE LAS VEGAS, NV 89102 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Elec/Plmb/HVAC | 11/24/2020 | Approved | STUART CHAPMAN |
| Wood Frame | 11/24/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 12/30/2020 | Approved | SCOTT FINNILA |
| Shower Pan | 12/30/2020 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/12/2021 | Approved | SCOTT FINNILA |
| Final | 5/12/2021 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/12/2021 | Partial Inspection | SCOTT FINNILA |
| METHANE-Barrier | 5/12/2021 | Approved | SCOTT FINNILA |
| METHANE-Final | 5/12/2021 | Approved | SCOTT FINNILA |
| METHANE-Rough | 5/12/2021 | Approved | SCOTT FINNILA |
| METHANE-Subgrade | 5/12/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 5/12/2021 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/20/2021 | No Access for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 5/25/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Final | 6/1/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/1/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/1/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |