2129 S ALSACE AVE 90016
Certificate Information: 2129 S ALSACE AVE 90016
- Application / Permit
- 20016-30000-07870
- Plan Check / Job No.
- B20WL01382
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel of existing SFD. Remove interior walls, add ceiling beams, remodel kitchen & bathroom, relocate 1 bathroom and add 1 bathroom, change all windows, relocate 2 windows. all work per engineering.
- Permit Issued
- Issued on 4/16/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/19/2020
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | MANUEL GARCIA |
| Corrections Issued | 3/19/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 4/1/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 4/8/2020 | VLADIMIR ARUTYUNYAN |
| No Progress | 4/8/2020 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 4/10/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 4/16/2020 | LADBS |
| Building Plans Picked Up | 4/16/2020 | APPLICANT |
| Permit Finaled | 9/18/2020 | STUART CHAPMAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/21/2020 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/21/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 4/21/2020 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 4/21/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/21/2020 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/30/2020 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/30/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 4/30/2020 | Approved | STUART CHAPMAN |
| Insulation | 4/30/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 5/12/2020 | Approved | STUART CHAPMAN |
| Final | 6/23/2020 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/23/2020 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 6/23/2020 | Approved | STUART CHAPMAN |
| Final | 7/31/2020 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 7/31/2020 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 7/31/2020 | SGSOV Approved | STUART CHAPMAN |
| Final | 8/12/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 9/18/2020 | Permit Finaled | STUART CHAPMAN |