267 S OCEANO DR 90049

Certificate Information: 267 S OCEANO DR 90049

Application / Permit
20016-30000-07781
Plan Check / Job No.
B20WL01363
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
T.I. OF (E) 2-story SFD WITH ATTACHED GARAGE . RE-CONFIGURATION OF (E) SPACES ON THE GROUND FLOOR. PORTION OF (E) ROOF TO BE RE-FRAMED W/ TALLER PLATE HEIGHT. DOORS & WINDOWS TO BE REPLACED. (N) ROOF MATERIAL ON (E) ROOF. (N) TRELLIS @ GROUND LEVEL, REMOVE & REPLACES INTERIOR STAIRS, BATHROOMS, & KITCHEN REMODEL.
Permit Issued
Issued on 3/22/2021
Issuing Office
Metro
Current Status
Permit Finaled on 3/17/2023

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/24/2020 TARIK SAOUD
Corrections Issued 3/25/2020 TARIK SAOUD
Quality Review Completed 4/1/2020 CORA JOHNSON
Green Plans Picked Up 6/25/2020 APPLICANT
Applicant returned to address corrections 11/12/2020 TARIK SAOUD
Applicant returned to address corrections 12/14/2020 TARIK SAOUD
Applicant returned to address corrections 12/15/2020 TARIK SAOUD
Plan Check Approved 12/17/2020 TARIK SAOUD
Building Plans Picked Up 12/18/2020 APPLICANT
Issued 3/22/2021 APPLICANT
Permit Finaled 3/17/2023 STEPHANIE SWANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/20/2020 DINAH GARIN
Green Code Cleared 6/16/2020 RICHARD GARCIA
Low Impact Development Cleared 10/5/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 10/30/2020 DINAH GARIN
Grading Pre-Inspection Cleared 12/15/2020 TARIK SAOUD

Contact Information

Contractor A List Builders Inc; Lic. No.: 952112-B 13237 CHANDLER BLVD      SHERMAN OAKS, CA 91401
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 708 SOUTH REDONDO AVE      MANHATTAN BEACH, CA 90266

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/7/2021 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 5/7/2021 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 5/14/2021 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/14/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 7/28/2021 Corrections Issued ANTHONY MCDOWALL
HVAC-Rough 7/28/2021 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Rough 7/28/2021 Corrections Issued ANTHONY MCDOWALL
PLUMBING-Rough 8/16/2021 Approved JOHN KIDWELL
Deputy Wood Construction 8/26/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 8/26/2021 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Approved JOHN KIDWELL
HVAC-Rough 8/26/2021 Approved JOHN KIDWELL
Shower Pan 9/24/2021 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 10/20/2021 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 10/20/2021 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 10/26/2021 Corrections Issued JOHN KIDWELL
Interior/Exterior Lathing 10/26/2021 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 11/10/2021 Approved JOHN KIDWELL
Insulation 11/10/2021 Approved JOHN KIDWELL
Drywall Nailing 1/6/2022 Approved JOHN KIDWELL
ELECTRICAL-Final 6/9/2022 Approved JOHN KIDWELL
PLUMBING-Final 6/9/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 6/9/2022 Approved JOHN KIDWELL
Final 1/5/2023 Corrections Issued KEVIN SARGSYAN
Green Building Final 1/5/2023 Approved KEVIN SARGSYAN
HVAC-Final 1/5/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/5/2023 SGSOV Not Ready KEVIN SARGSYAN
Final 3/17/2023 Permit Finaled STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved STEPHANIE SWANSON