267 S OCEANO DR 90049
Certificate Information: 267 S OCEANO DR 90049
- Application / Permit
- 20016-30000-07781
- Plan Check / Job No.
- B20WL01363
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- T.I. OF (E) 2-story SFD WITH ATTACHED GARAGE . RE-CONFIGURATION OF (E) SPACES ON THE GROUND FLOOR. PORTION OF (E) ROOF TO BE RE-FRAMED W/ TALLER PLATE HEIGHT. DOORS & WINDOWS TO BE REPLACED. (N) ROOF MATERIAL ON (E) ROOF. (N) TRELLIS @ GROUND LEVEL, REMOVE & REPLACES INTERIOR STAIRS, BATHROOMS, & KITCHEN REMODEL.
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/17/2023
Permit Application Status History
| Submitted | 3/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2020 | TARIK SAOUD |
| Corrections Issued | 3/25/2020 | TARIK SAOUD |
| Quality Review Completed | 4/1/2020 | CORA JOHNSON |
| Green Plans Picked Up | 6/25/2020 | APPLICANT |
| Applicant returned to address corrections | 11/12/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 12/14/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 12/15/2020 | TARIK SAOUD |
| Plan Check Approved | 12/17/2020 | TARIK SAOUD |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| Issued | 3/22/2021 | APPLICANT |
| Permit Finaled | 3/17/2023 | STEPHANIE SWANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2020 | DINAH GARIN |
| Green Code | Cleared | 6/16/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 10/5/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 12/15/2020 | TARIK SAOUD |
Contact Information
| Contractor | A List Builders Inc; Lic. No.: 952112-B | 13237 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 708 SOUTH REDONDO AVE MANHATTAN BEACH, CA 90266 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 5/14/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/14/2021 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 7/28/2021 | Corrections Issued | ANTHONY MCDOWALL |
| HVAC-Rough | 7/28/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 7/28/2021 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 8/16/2021 | Approved | JOHN KIDWELL |
| Deputy Wood Construction | 8/26/2021 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/26/2021 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Approved | JOHN KIDWELL |
| HVAC-Rough | 8/26/2021 | Approved | JOHN KIDWELL |
| Shower Pan | 9/24/2021 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/20/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/20/2021 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/26/2021 | Corrections Issued | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/26/2021 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/10/2021 | Approved | JOHN KIDWELL |
| Insulation | 11/10/2021 | Approved | JOHN KIDWELL |
| Drywall Nailing | 1/6/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 6/9/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 6/9/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/9/2022 | SGSOV Not Ready | JOHN KIDWELL |
| Smoke Detectors | 6/9/2022 | Approved | JOHN KIDWELL |
| Final | 1/5/2023 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 1/5/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 1/5/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Not Ready | KEVIN SARGSYAN |
| Final | 3/17/2023 | Permit Finaled | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Approved | STEPHANIE SWANSON |