2649 S DUNSMUIR AVE 90016
Certificate Information: 2649 S DUNSMUIR AVE 90016
- Application / Permit
- 20016-30000-07659
- Plan Check / Job No.
- B20WL01335
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- convert (e) detached garage to adu
- Permit Issued
- Issued on 4/21/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | TARIK SAOUD |
| Corrections Issued | 3/23/2020 | TARIK SAOUD |
| Plan Check Approved | 4/14/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 4/21/2020 | LADBS |
| Building Plans Picked Up | 5/1/2020 | APPLICANT |
| CofO in Progress | 12/2/2020 | DAVID CHAN |
| Permit Finaled | 2/17/2023 | DANIEL ORRANTE |
| CofO Issued | 2/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 3/26/2020 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/13/2020 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/22/2020 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 6/12/2020 | Not Ready for Inspection | DAVID CHAN |
| PLUMBING-Rough | 6/12/2020 | Not Ready for Inspection | DAVID CHAN |
| Interior/Exterior Lathing | 6/22/2020 | Corrections Issued | DAVID CHAN |
| PLUMBING-Rough | 6/22/2020 | Not Ready for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 6/23/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Rough | 6/23/2020 | Approved | DAVID CHAN |
| Green Building Rough | 6/23/2020 | Approved | DAVID CHAN |
| MERV13>=Rough | 6/23/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 6/29/2020 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 7/2/2020 | Approved | DAVID CHAN |
| Pre-Inspection | 7/2/2020 | Partial Inspection | DAVID CHAN |
| Drywall Nailing | 7/13/2020 | Approved | THOMAS LOGRASSO |
| Gas Test | 7/23/2020 | Corrections Issued | RUBEN SALAS |
| Gas Test | 8/7/2020 | Corrections Issued | THOMAS LOGRASSO |
| Gas Test | 8/10/2020 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/21/2020 | Not Ready for Inspection | DAVID CHAN |
| Final | 8/21/2020 | Corrections Issued | DAVID CHAN |
| Green Building Final | 8/21/2020 | Approved | DAVID CHAN |
| HVAC-Final | 8/21/2020 | Approved | DAVID CHAN |
| MERV13>=Final | 8/21/2020 | Approved | DAVID CHAN |
| PLUMBING-Final | 8/21/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Approved | DAVID CHAN |
| Smoke Detectors | 8/21/2020 | Approved | DAVID CHAN |
| Final | 9/2/2020 | Not Ready for Inspection | DAVID CHAN |
| Service/Power Release | 9/2/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 11/17/2020 | Approved | SCOTT FINNILA |
| Final | 11/17/2020 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 11/17/2020 | Approved | SCOTT FINNILA |
| HVAC-Final | 11/17/2020 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 11/17/2020 | Approved | SCOTT FINNILA |
| Final | 12/1/2020 | OK to Issue CofO | DAVID CHAN |