5556 W WASHINGTON BLVD 90016

Certificate Information: 5556 W WASHINGTON BLVD 90016

Application / Permit
20016-30000-07394
Plan Check / Job No.
B20WL01276
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TENANT IMPROVEMENT TO (E) OFFICE. NO CHANGE IN USE. INCLUDES NEW NON-STRUCTURAL PARTITIONS, RELOCATED BATHROOMS. STRUCTURAL UPGRADES INCLUDE NE SHEAR WALLS AND REINFORCED ROOF STRUCTURE. NO ADDITIONAL S.F. ADDED.
Permit Issued
Issued on 8/3/2020
Issuing Office
Current Status
Permit Finaled on 10/18/2021

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 MANUEL GARCIA
Corrections Issued 4/8/2020 MANUEL GARCIA
Quality Review Completed 4/17/2020 KAMRAN GHOTBI RAVANDI
Disabled Access Plans Picked Up 6/26/2020 APPLICANT
Plan Check Approved 7/15/2020 MANUEL GARCIA
Issued 8/3/2020 APPLICANT
Building Plans Picked Up 8/13/2020 APPLICANT
Permit Finaled 10/18/2021 TIMOTHY BUXTON

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 5/29/2020 KYLE WINSTON
ZI Cleared 5/29/2020 KYLE WINSTON
Eng Process Fee Ord 176,300 Cleared 6/29/2020 CELINA MORENO
Sewer availability Cleared 6/29/2020 CELINA MORENO
DAS Clearance Cleared 6/30/2020 SOMKIAT SUPANYACHOTSKUL

Contact Information

Contractor Makeover Builders Inc; Lic. No.: 986740-B 21781 VENTURA BLVD UNIT 634      WOODLAND HILLS, CA 91364
Engineer Chikhale,, Jonathan William; Lic. No.: C78893 2820 MILITARY AVENUE      LOS ANGELES, CA 90064

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/19/2020 Conditional Approval TIMOTHY BUXTON
Footing/Foundation/Slab 8/19/2020 Approved TIMOTHY BUXTON
Deputy Drilled-In Anchors 10/13/2020 Conditional Approval JONATHAN QUACH
Wood Frame 10/19/2020 Not Ready for Inspection TIMOTHY BUXTON
Wood Frame 12/21/2020 Approved TIMOTHY BUXTON
Drywall Nailing 12/28/2020 Approved TIMOTHY BUXTON
Insulation 12/28/2020 Approved TIMOTHY BUXTON
Interior/Exterior Lathing 12/28/2020 Approved TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 10/14/2021 Not Ready for Inspection KATY RAMIREZ
Final 10/18/2021 Permit Finaled TIMOTHY BUXTON
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV No Gas TIMOTHY BUXTON
Smoke Detectors 10/18/2021 Approved TIMOTHY BUXTON