259 3/4 W ISABEL ST 90065
Certificate Information: 259 3/4 W ISABEL ST 90065
- Application / Permit
- 20016-30000-07338
- Plan Check / Job No.
- B20WL01264
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF THE EXISTING GROUND FLOOR STORAGE INTO AN ACCESSORY DWELLING UNIT IN A SINGLE FAMILY DWELLING PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/14/2020
- Issuing Office
- Current Status
- CofO Issued on 3/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | PARISA ZAHABI |
| Corrections Issued | 3/19/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 5/20/2020 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 6/11/2020 | DAVID CASTILLO |
| Applicant returned to address corrections | 6/25/2020 | JASON JANGADA |
| Plan Check Approved | 7/8/2020 | ALFREDO JARA |
| Issued | 7/14/2020 | APPLICANT |
| Building Plans Picked Up | 7/15/2020 | APPLICANT |
| CofO in Progress | 3/1/2021 | OSVALDO PARAMO |
| Permit Finaled | 3/6/2021 | DEROLD HAUFF |
| CofO Issued | 3/6/2021 | DEROLD HAUFF |
| Permit Finaled | 3/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2020 | CELINA MORENO |
| Sewer availability | Cleared | 4/3/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2020 | ELAINE LEI |
| Tenant Habitability Plan | Cleared | 4/27/2020 | STEVEN HOFSTAD |
| Specific Plan | Cleared | 5/14/2020 | NASHYA JENSEN |
| ZI | Cleared | 5/14/2020 | NASHYA JENSEN |
Contact Information
| Contractor | Aiden'S Structural Concepts; Lic. No.: 922303-B | 13230 BROMONT AVE #111 SYLMAR, CA 91342 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/17/2020 | No Access for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 12/21/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 1/11/2021 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 1/11/2021 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 1/11/2021 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 1/11/2021 | Not Ready for Inspection | RUBEN SALAS |
| Shower Pan | 1/11/2021 | Approved | RUBEN SALAS |
| BUILDING-Rough-Frame | 1/14/2021 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 1/14/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 1/21/2021 | Approved | OSVALDO PARAMO |
| Insulation | 1/21/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 1/21/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 1/21/2021 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 1/25/2021 | Approved | OSVALDO PARAMO |
| Service/Power Release | 1/29/2021 | Corrections Issued | CRAIG VAUGHAN |
| Final | 2/12/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/12/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 2/12/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 2/19/2021 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 2/19/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 2/19/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 2/26/2021 | Approved | OSVALDO PARAMO |
| Final | 2/26/2021 | OK to Issue CofO | OSVALDO PARAMO |
| HVAC-Final | 2/26/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 2/26/2021 | Approved | OSVALDO PARAMO |
| Service/Power Release | 2/26/2021 | Approved | OSVALDO PARAMO |