750 N CITRUS AVE 90038

Certificate Information: 750 N CITRUS AVE 90038

Application / Permit
20016-30000-06876
Plan Check / Job No.
B20WL01174
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) DETACHED GARAGE INTO AN ADU AT REAR OF THE LOT, MAINTAINING A 2-CAR GARAGE AFTER CONVERSION, PER CA G.C.S. 65852.2(e)(1)(A).
Permit Issued
Issued on 9/30/2020
Issuing Office
Current Status
CofO Issued on 1/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2020 APPLICANT
Assigned to Plan Check Engineer 3/25/2020 JAHANSHAH POURHASSAN
Corrections Issued 4/2/2020 JAHANSHAH POURHASSAN
Quality Review Completed 4/24/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 4/29/2020 APPLICANT
Applicant returned to address corrections 6/2/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/3/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/19/2020 JAHANSHAH POURHASSAN
Plan Check Approved 9/24/2020 JAHANSHAH POURHASSAN
Issued 9/30/2020 APPLICANT
Building Plans Picked Up 10/2/2020 APPLICANT
CofO in Progress 1/13/2021 BRIAN SULLIVAN
Permit Finaled 1/23/2021 DEROLD HAUFF
Permit Finaled 1/23/2021 DEROLD HAUFF
CofO Issued 1/23/2021 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 4/20/2020 JEREMY CORONEL
Green Code Cleared 5/22/2020 RICHARD GARCIA
Address approval Cleared 6/4/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/4/2020 RENZ SORIANO
Construction near power lines Cleared 7/16/2020 WALTER RAMIREZ

Contact Information

Contractor Nelson General Building Contractor; Lic. No.: 649194-B 4227 S WESTERN AVE      LOS ANGELES, CA 90062
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2020 Partial Approval BRIAN SULLIVAN
Underground Mechanical 10/8/2020 Approved BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/15/2020 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 10/15/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 10/28/2020 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 10/28/2020 Conditional Approval RAUL BARAJAS
METHANE-Rough 10/28/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 10/28/2020 Not Ready for Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 10/28/2020 Not Ready for Inspection RAUL BARAJAS
Insulation 11/4/2020 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 11/4/2020 Partial Approval JOSEPH MCGARRY
Underground Mechanical 11/4/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 11/6/2020 Approved JOSEPH MCGARRY
METHANE-Rough 11/6/2020 Approved JOSEPH MCGARRY
Drywall Nailing 11/13/2020 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 11/13/2020 Approved BRIAN SULLIVAN
Shower Pan 11/13/2020 Approved BRIAN SULLIVAN
ELECTRICAL-Final 11/30/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 11/30/2020 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 11/30/2020 Not Ready for Inspection BRIAN SULLIVAN
Drywall Nailing 12/15/2020 Approved RAUL BARAJAS
Final 12/15/2020 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Approved RAUL BARAJAS
Smoke Detectors 12/15/2020 Approved RAUL BARAJAS
Final 1/13/2021 OK to Issue CofO BRIAN SULLIVAN