4558 N SALTILLO ST 91364
Certificate Information: 4558 N SALTILLO ST 91364
- Application / Permit
- 20016-30000-06846
- Plan Check / Job No.
- B20WL01169
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18' X 18' 1 1/2" (E) GARAGE TO ADU PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- CofO Issued on 9/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2020 | PARISA ZAHABI |
| Corrections Issued | 3/18/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 7/23/2020 | JASON JANGADA |
| Applicant returned to address corrections | 10/28/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 11/28/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 3/17/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 5/19/2021 | PARISA ZAHABI |
| Plan Check Approved | 6/22/2021 | PARISA ZAHABI |
| Issued | 6/24/2021 | APPLICANT |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| CofO in Progress | 4/8/2022 | PETER FOLLING |
| No Progress | 7/21/2022 | ROBERT GOLD |
| CofO in Progress | 9/28/2022 | SEAN WIRCH |
| Permit Finaled | 9/29/2022 | JOHN JANSON |
| CofO Issued | 9/29/2022 | JOHN JANSON |
| Permit Finaled | 9/29/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/24/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/24/2020 | GABRIEL ROBLES |
| Specific Plan | Cleared | 2/26/2021 | OLGA AYALA |
| Specific Plan | Cleared | 2/26/2021 | OLGA AYALA |
| ZI | Cleared | 2/26/2021 | OLGA AYALA |
| ZI | Cleared | 2/26/2021 | OLGA AYALA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/8/2021 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 7/8/2021 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 7/8/2021 | Not Ready for Inspection | PETER FOLLING |
| Deputy Drilled-In Anchors | 7/19/2021 | No Access for Inspection | PETER FOLLING |
| PLUMBING-Rough | 7/20/2021 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 7/26/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 8/3/2021 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 8/3/2021 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 8/9/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 8/12/2021 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 9/23/2021 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 9/23/2021 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 11/18/2021 | Approved | PETER FOLLING |
| PLUMBING-Rough | 11/18/2021 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 12/17/2021 | Partial Approval | PETER FOLLING |
| ELECTRICAL-Rough | 12/17/2021 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | PETER FOLLING |
| Interior/Exterior Lathing | 12/17/2021 | Partial Approval | PETER FOLLING |
| BUILDING-Rough-Frame | 12/29/2021 | Approved | PETER FOLLING |
| Insulation | 12/29/2021 | Approved | PETER FOLLING |
| Drywall Nailing | 1/13/2022 | Approved | JUSTIN HAWLEY |
| Final | 3/22/2022 | Corrections Issued | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 3/22/2022 | Approved | PETER FOLLING |
| Wood Frame | 3/22/2022 | Approved | PETER FOLLING |
| Final | 4/5/2022 | OK to Issue CofO | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 4/5/2022 | SGSOV Approved | PETER FOLLING |