5734 W BURCHARD AVE 90034

Certificate Information: 5734 W BURCHARD AVE 90034

Application / Permit
20016-30000-06384
Plan Check / Job No.
B20WL01092
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND STORAGE AT REAR OF THE LOT TO AN ADU PER CA G.C.S. 65852.2(e)(1)(A).
Permit Issued
Issued on 4/4/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/11/2020 PARISA ZAHABI
Corrections Issued 3/12/2020 PARISA ZAHABI
Applicant returned to address corrections 9/8/2021 JASON JANGADA
Applicant returned to address corrections 11/2/2021 KHUONG TRUONG
Applicant returned to address corrections 12/21/2021 JAHANSHAH POURHASSAN
Plan Check Approved 2/1/2022 ALFREDO JARA
Building Plans Picked Up 2/2/2022 APPLICANT
Issued 4/4/2022 APPLICANT
CofO in Progress 7/13/2023 ARAM AVEDISIAN
Permit Finaled 7/24/2023 DANIEL ORRANTE
CofO Issued 7/24/2023 DANIEL ORRANTE
Permit Finaled 7/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

"Q" conditions Cleared 8/12/2021 DENZEL HENDERSON
Address approval Cleared 8/16/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/18/2021 STEVE MELGAR
Construction near power lines Cleared 10/21/2021 OSCAR CASTRO
Tenant Habitability Plan Cleared 12/1/2021 PHILLIP MUNGUIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2022 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 6/9/2022 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 6/13/2022 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 7/15/2022 Not Ready for Inspection EVAN COOPER
Green Building Rough 7/15/2022 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 7/15/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 7/15/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 7/21/2022 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 8/5/2022 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 8/12/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/17/2022 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 8/17/2022 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 8/25/2022 Partial Approval JOHNNY MIRANDA
Insulation 9/7/2022 Not Ready for Inspection EVAN COOPER
Insulation 9/9/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Partial Approval JOHN KIDWELL
Drywall Nailing 9/20/2022 Approved EVAN COOPER
HVAC-Rough 9/20/2022 Corrections Issued EVAN COOPER
Gas Test 10/5/2022 Approved EVAN COOPER
Service/Power Release 10/27/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 2/21/2023 Approved JEREMY TODD
Final 2/21/2023 Corrections Issued JEREMY TODD
Green Building Final 2/21/2023 Approved JEREMY TODD
Green Building Rough 2/21/2023 Approved JEREMY TODD
MERV13>=Final 2/21/2023 Approved JEREMY TODD
MERV13>=Rough 2/21/2023 Approved JEREMY TODD
Smoke Detectors 2/21/2023 Approved JEREMY TODD
Special/Order Compliance 2/27/2023 Partial Inspection JEREMY TODD
ELECTRICAL-Final 5/23/2023 Corrections Issued JEREMY TODD
ELECTRICAL-Final 6/7/2023 Approved JEREMY TODD
HVAC-Final 6/7/2023 Approved JEREMY TODD
PLUMBING-Final 6/7/2023 Approved JEREMY TODD
Final 7/13/2023 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 7/13/2023 Approved ARAM AVEDISIAN