7611 W 83RD ST 90293

Certificate Information: 7611 W 83RD ST 90293

Application / Permit
20016-30000-06316
Plan Check / Job No.
B20WL01081
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MASTER BATH REMODEL, DOWNSTAIRS BATHROOM REMODEL, FAMILY RM/ KITCHEN REMODEL INSTEAD OF 2 SLIDING DOORS ONE PANORAMIC SLIDING/STACKING DOOR, ADD SMALL STACK WASHER & DRYER TO LINEN CLOSET. CANCEL FAMILY ROOM FIREPLCAE CAP OFF
Permit Issued
Issued on 3/18/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 11/18/2020

Permit Application Status History

Submitted 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SERGIO SILVA
Corrections Issued 3/10/2020 SERGIO SILVA
Building Plans Picked Up 3/12/2020 APPLICANT
Plan Check Approved 3/17/2020 SERGIO SILVA
Issued 3/18/2020 LADBS
Permit Finaled 11/18/2020 JUAN VALENZUELA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/12/2020 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Sims,, Bradley Alan; Lic. No.: C58238 5732 WALTON ST      LONG BEACH, CA 90815

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/21/2020 Conditional Approval CRAIG DAVIS
Footing/Foundation/Slab 4/22/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 4/27/2020 Approved JUAN VALENZUELA
Deputy Steel/Welding 5/13/2020 No Access for Inspection CRAIG DAVIS
Deputy Steel/Welding 5/22/2020 Conditional Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 6/15/2020 No Access for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 6/29/2020 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 6/29/2020 Approved JUAN VALENZUELA
Deputy Drilled-In Anchors 7/8/2020 Conditional Approval JUAN VALENZUELA
Interior/Exterior Lathing 7/15/2020 Partial Approval JUAN VALENZUELA
Shower Pan 7/15/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 7/23/2020 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 8/5/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 8/5/2020 Approved JUAN VALENZUELA
Insulation 8/6/2020 Approved JUAN VALENZUELA
Drywall Nailing 8/11/2020 Approved JUAN VALENZUELA
Final 11/18/2020 Permit Finaled JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 11/18/2020 Approved JUAN VALENZUELA