2618 S BENTLEY AVE 90064

Certificate Information: 2618 S BENTLEY AVE 90064

Application / Permit
20016-30000-05922
Plan Check / Job No.
B20WL01011
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert Garage into ADU per State Law.
Permit Issued
Issued on 6/25/2020
Issuing Office
Current Status
CofO Issued on 4/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MANUEL GARCIA
Corrections Issued 3/24/2020 MANUEL GARCIA
Quality Review Completed 4/2/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/4/2020 MANUEL GARCIA
Plan Check Approved 6/16/2020 MANUEL GARCIA
Building Plans Picked Up 6/17/2020 APPLICANT
Issued 6/25/2020 APPLICANT
CofO in Progress 3/5/2021 RICHARD ROBLES
Permit Finaled 4/15/2022 DANIEL ORRANTE
CofO Issued 4/15/2022 DANIEL ORRANTE
Permit Finaled 4/15/2022 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 5/4/2020 ANNA VIDAL
Specific Plan Cleared 5/4/2020 ANNA VIDAL
Address approval Cleared 5/5/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/5/2020 DINAH GARIN
Sewer availability Cleared 5/5/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 5/15/2020 DINAH GARIN
Green Code Cleared 5/27/2020 RICHARD GARCIA
Green Code Cleared 5/27/2020 RICHARD GARCIA
Grading Pre-Inspection Cleared 6/4/2020 MANUEL GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/28/2020 Corrections Issued OGANES TARAKHCHYAN
Underground Mechanical 7/29/2020 Partial Approval OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 7/30/2020 Corrections Issued OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 8/3/2020 Approved EVAN COOPER
Smoke Detectors 8/3/2020 Not Ready for Inspection EVAN COOPER
Insulation 8/4/2020 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/5/2020 Partial Approval OGANES TARAKHCHYAN
Gas Test 8/5/2020 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 8/5/2020 Approved OGANES TARAKHCHYAN
MERV13>=Rough 8/5/2020 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Rough 8/5/2020 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 8/6/2020 Approved OGANES TARAKHCHYAN
Insulation 8/6/2020 Approved OGANES TARAKHCHYAN
Drywall Nailing 8/11/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 8/11/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/1/2021 Corrections Issued RICHARD ROBLES
ELECTRICAL-Final 3/1/2021 Corrections Issued RICHARD ROBLES
Final 3/1/2021 Not Ready for Inspection RICHARD ROBLES
Green Building Final 3/1/2021 Approved RICHARD ROBLES
HVAC-Final 3/1/2021 Approved RICHARD ROBLES
MERV13>=Final 3/1/2021 Approved RICHARD ROBLES
MERV13>=Rough 3/1/2021 Approved RICHARD ROBLES
METHANE-Final 3/1/2021 Approved RICHARD ROBLES
METHANE-Rough 3/1/2021 Approved RICHARD ROBLES
PLUMBING-Final 3/1/2021 Corrections Issued RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 3/1/2021 SGSOV Approved RICHARD ROBLES
Smoke Detectors 3/1/2021 Approved RICHARD ROBLES
BUILDING-Rough-Frame 3/4/2021 Approved RICHARD ROBLES
Final 3/4/2021 OK to Issue CofO RICHARD ROBLES
Service/Power Release 3/4/2021 Approved RICHARD ROBLES