1244 N MORAGA DR 90049
Certificate Information: 1244 N MORAGA DR 90049
- Application / Permit
- 20016-30000-05469
- Plan Check / Job No.
- B20WL00929
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- OPEN THE 170SF COVERED LOGGIA , REMOVE (E) DOORS ON EXTERIOR SIDE OF LOGGIA AND REPLACE WITH A (N) BEAM AND TWO COLUMNS ON THE SIDES. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/28/2020
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 3/4/2022
Permit Application Status History
| Submitted | 2/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2020 | PARISA ZAHABI |
| Corrections Issued | 3/6/2020 | PARISA ZAHABI |
| Plan Check Approved | 3/11/2020 | PARISA ZAHABI |
| Issued | 5/28/2020 | LADBS |
| Permit Finaled | 3/4/2022 | CARLOS MATAMOROS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | J R C Group Inc; Lic. No.: 980658-B | 8981 SUNSET BLVD STE 505 LOS ANGELES, CA 90069 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: C40985 | 30423 CANWOOD ST STE 223 AGOURA HILLS, CA 91301 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/7/2020 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 7/7/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/5/2020 | Partial Approval | CARLOS MATAMOROS |
| Pre-Inspection | 8/7/2020 | Corrections Issued | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 12/3/2020 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/21/2020 | Approved | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 12/21/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 1/20/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Shower Pan | 1/20/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Insulation | 1/22/2021 | Approved | CARLOS MATAMOROS |
| Shower Pan | 1/22/2021 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 2/17/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/17/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/3/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/10/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 3/12/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/4/2022 | Approved | CARLOS MATAMOROS |
| Final | 3/4/2022 | Permit Finaled | CARLOS MATAMOROS |
| HVAC-Final | 3/4/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 3/4/2022 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 3/4/2022 | Approved | CARLOS MATAMOROS |