21539 W MULHOLLAND DR 91364
Certificate Information: 21539 W MULHOLLAND DR 91364
- Application / Permit
- 20016-30000-05130
- Plan Check / Job No.
- B20WL00862
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (e) attached garage to ADU per ordinance and addition.
- Permit Issued
- Issued on 11/6/2020
- Issuing Office
- Current Status
- CofO Issued on 3/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | PARISA ZAHABI |
| Corrections Issued | 2/28/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 3/12/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/28/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 10/21/2020 | RICHARD GARCIA |
| Plan Check Approved | 10/29/2020 | RICHARD GARCIA |
| Issued | 11/6/2020 | APPLICANT |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| CofO in Progress | 9/10/2021 | PETER FOLLING |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
| CofO Issued | 3/6/2022 | MICHAEL SMITH |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 3/12/2020 | DOMINIQUE MEDINA |
| Sewer availability | Cleared | 3/12/2020 | ANTHONY MAINEZ |
| ZI | Cleared | 9/25/2020 | DOMINICK ORTIZ |
| ZI | Cleared | 9/25/2020 | DOMINICK ORTIZ |
| Grading Pre-Inspection | Cleared | 10/6/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manesh,, Behnam Abraham; Lic. No.: C38454 | 17337 VENTURA BLVD STE 112 ENCINO, CA 91316 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/13/2020 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 11/30/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Sewer | 11/30/2020 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/3/2020 | Corrections Issued | DONALD SUNSERI |
| Sewer | 12/3/2020 | Corrections Issued | DONALD SUNSERI |
| Footing/Foundation/Slab | 12/7/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/7/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 12/7/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/13/2021 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/13/2021 | Partial Approval | VINCENT HANLEY |
| Gas Test | 1/13/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 1/13/2021 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/25/2021 | Corrections Issued | PAUL CHOPP |
| ELECTRICAL-Rough | 1/25/2021 | Corrections Issued | PAUL CHOPP |
| HVAC-Rough | 1/25/2021 | Approved | PAUL CHOPP |
| Verify Sprinkler Sign Off | 1/25/2021 | Corrections Issued | PAUL CHOPP |
| BUILDING-Rough-Frame | 5/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 5/19/2021 | Approved | DAVID SANDOVAL |
| Gas Test | 5/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 5/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 5/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/2/2021 | Approved | PETER FOLLING |
| Gas Test | 6/2/2021 | Approved | PETER FOLLING |
| PLUMBING-Rough | 6/2/2021 | Approved | PETER FOLLING |
| Verify Sprinkler Sign Off | 6/2/2021 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 6/8/2021 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/11/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 6/16/2021 | No Access for Inspection | DAVID SANDOVAL |
| Drywall Nailing | 6/22/2021 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 8/5/2021 | Not Ready for Inspection | PETER FOLLING |
| Final | 8/5/2021 | Corrections Issued | PETER FOLLING |
| HVAC-Final | 8/5/2021 | Corrections Issued | PETER FOLLING |
| PLUMBING-Final | 8/5/2021 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 8/5/2021 | SGSOV Gas Company | PETER FOLLING |
| Smoke Detectors | 8/5/2021 | Approved | PETER FOLLING |
| Final | 8/31/2021 | Corrections Issued | PETER FOLLING |
| Final | 9/9/2021 | OK to Issue CofO | PETER FOLLING |