1219 E ELM ST 90291
Certificate Information: 1219 E ELM ST 90291
- Application / Permit
- 20016-30000-04577
- Plan Check / Job No.
- B20WL00768
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 23'-2"X 15'-6" ATTACHED STORAGE TO (E) GARAGE INTO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 4/14/2020
- Issuing Office
- Current Status
- CofO Issued on 9/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | PARISA ZAHABI |
| Corrections Issued | 2/20/2020 | PARISA ZAHABI |
| Plan Check Approved | 4/8/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 4/14/2020 | APPLICANT |
| Building Plans Picked Up | 4/30/2020 | APPLICANT |
| CofO in Progress | 9/17/2020 | CRAIG DAVIS |
| CofO Issued | 9/21/2020 | VINCENT COTTON |
| Permit Finaled | 9/21/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2020 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2020 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 3/4/2020 | DENNIS BRAGIN |
| Sewer availability | Cleared | 3/4/2020 | DENNIS BRAGIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/5/2020 | Partial Inspection | JOHNNY MIRANDA |
| Sewer | 5/6/2020 | Corrections Issued | CRAIG DAVIS |
| Sewer | 5/6/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 5/11/2020 | Partial Approval | DAVID FEILER |
| Sewer | 5/12/2020 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 5/28/2020 | Approved | DAVID FEILER |
| HVAC-Rough | 5/28/2020 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 6/5/2020 | Partial Approval | JUAN VALENZUELA |
| Wood Frame | 6/5/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/9/2020 | Approved | CRAIG DAVIS |
| Insulation | 6/9/2020 | Approved | CRAIG DAVIS |
| Rough-Elec/Plmb/HVAC | 6/9/2020 | Approved | CRAIG DAVIS |
| Drywall Nailing | 6/15/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/15/2020 | Approved | EVAN COOPER |
| Shower Pan | 6/15/2020 | Approved | EVAN COOPER |
| Final | 8/17/2020 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 8/17/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 8/17/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/21/2020 | Approved | CRAIG DAVIS |
| HVAC-Final | 8/21/2020 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 8/21/2020 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 9/3/2020 | Partial Approval | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 9/3/2020 | Approved | CRAIG DAVIS |
| Final | 9/16/2020 | OK to Issue CofO | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 9/16/2020 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 9/16/2020 | Approved | CRAIG DAVIS |