28118 S WESTERN AVE 90732
Certificate Information: 28118 S WESTERN AVE 90732
- Application / Permit
- 20016-30000-04403
- Plan Check / Job No.
- B20WL00755
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Beauty Shop or Parlor
- Work Description
- Non-struct'l T.I. and change of use from "RETAIL" to "BEAUTY SALON" No change in parking.
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- CofO Issued on 2/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | REZA HAGHIGHAT |
| Corrections Issued | 3/16/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 3/27/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/1/2020 | REZA HAGHIGHAT |
| Green Plans Picked Up | 8/12/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 8/27/2020 | APPLICANT |
| Plan Check Approved | 9/10/2020 | REZA HAGHIGHAT |
| Issued | 9/10/2020 | APPLICANT |
| Building Plans Picked Up | 9/15/2020 | APPLICANT |
| TCO Issued (Expire Date: 06-26-2021) | 12/28/2020 | NICK LAROCCA |
| CofO in Progress | 2/18/2021 | JOEY BUCHANAN |
| Permit Finaled | 2/26/2021 | HENRY BAGHDASSARIAN |
| CofO Issued | 2/26/2021 | HENRY BAGHDASSARIAN |
| Permit Finaled | 2/26/2021 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Green Code | Cleared | 4/29/2020 | RICHARD GARCIA |
| DAS Clearance | Cleared | 8/27/2020 | SOMKIAT SUPANYACHOTSKUL |
| "Q" conditions | Cleared | 9/3/2020 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2020 | CHINH DINH |
| Sewer availability | Cleared | 9/3/2020 | CHINH DINH |
| ZA Case | Cleared | 9/3/2020 | MAXFIELD VERMY |
Contact Information
| Architect | , ; Lic. No.: C33214 | 10 TOWN PLAZA #178 DURANGO, CO 81301 |
| Contractor | Huffman David Construction; Lic. No.: 643863-B | 2836 WINDSTONE GLEN ESCONDIDO, CA 92027 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 9/18/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 10/21/2020 | Conditional Approval | JOEY BUCHANAN |
| Drywall Nailing | 10/29/2020 | Approved | JOEY BUCHANAN |
| Partition/T-Bar Ceiling | 11/20/2020 | Conditional Approval | JOEY BUCHANAN |
| Green Building Final | 12/18/2020 | Approved | JOEY BUCHANAN |
| Final | 12/23/2020 | OK for TCO | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 12/23/2020 | Approved | JOEY BUCHANAN |