282 S CANYON VIEW DR 90049

Certificate Information: 282 S CANYON VIEW DR 90049

Application / Permit
20016-30000-03265
Plan Check / Job No.
B20WL00573
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) POOL HOUSE TO AN ACCESSORY DWELLING UNIT (ADU). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/18/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 PARISA ZAHABI
Corrections Issued 2/6/2020 PARISA ZAHABI
Building Plans Picked Up 2/11/2020 APPLICANT
Plan Check Approved 2/14/2020 REZA HAGHIGHAT
Issued 2/18/2020 LADBS
CofO in Progress 12/2/2020 JOHN KIDWELL
CofO in Progress 12/2/2020 JOHN KIDWELL
CofO in Progress 12/31/2020 JOHN KIDWELL
Permit Finaled 1/11/2021 VINCENT COTTON
CofO Issued 1/11/2021 VINCENT COTTON
Permit Finaled 1/11/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 2/11/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/11/2020 DINAH GARIN
Sewer availability Cleared 2/11/2020 DINAH GARIN

Contact Information

Contractor Core Development Group Inc; Lic. No.: 845288-B 1112 MONTANA AVE #204      SANTA MONICA, CA 90403
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/21/2020 Partial Approval DANNY TOLENTINO
ELECTRICAL-Rough 2/28/2020 Approved DANNY TOLENTINO
HVAC-Rough 2/28/2020 Corrections Issued DANNY TOLENTINO
Interior/Exterior Lathing 2/28/2020 Partial Approval DANNY TOLENTINO
BUILDING-Rough-Frame 3/12/2020 Approved DANNY TOLENTINO
FLOOD-Proofing Certificate 3/12/2020 Approved DANNY TOLENTINO
Insulation 3/13/2020 Conditional Approval TIM CHRISTENSEN
Drywall Nailing 3/23/2020 Approved DANNY TOLENTINO
Shower Pan 3/23/2020 Approved DANNY TOLENTINO
Interior/Exterior Lathing 4/28/2020 Partial Approval DANNY TOLENTINO
Underground Mechanical 6/9/2020 Partial Approval TIM CHRISTENSEN
ELECTRICAL-Final 7/30/2020 Not Ready for Inspection ROBERT SHELLY
ELECTRICAL-Final 8/19/2020 Corrections Issued TIM CHRISTENSEN
HVAC-Final 8/19/2020 Corrections Issued TIM CHRISTENSEN
PLUMBING-Final 8/19/2020 Corrections Issued TIM CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 8/19/2020 SGSOV Approved TIM CHRISTENSEN
Smoke Detectors 8/19/2020 Partial Approval TIM CHRISTENSEN
ELECTRICAL-Final 8/24/2020 Approved TIM CHRISTENSEN
HVAC-Final 8/28/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 8/28/2020 Approved JOHN KIDWELL
HVAC-Final 9/8/2020 Approved TIM CHRISTENSEN
Service/Power Release 11/20/2020 Approved JOHN KIDWELL
Final 11/23/2020 OK to Issue CofO JOHN KIDWELL
Smoke Detectors 11/23/2020 Approved JOHN KIDWELL