1230 S CABRILLO AVE 90291

Certificate Information: 1230 S CABRILLO AVE 90291

Application / Permit
20016-30000-02964
Plan Check / Job No.
B20WL00522
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Raise the roof height. "COMPLY WITH DEPARTMENT ORDER effective date 06/10/2008. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 10/14/2021
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 6/24/2024

Permit Application Status History

Submitted 1/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/31/2020 KAVIAN REFAHI
Corrections Issued 1/31/2020 KAVIAN REFAHI
Plan Check Approved 9/2/2021 RICHARD GARCIA
Issued 10/14/2021 APPLICANT
Permit Finaled 6/24/2024 ANDREW BEELI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/10/2020 TRACY TATE
Specific Plan Cleared 12/11/2020 BINDU KANNAN
Coastal Zone Cleared 12/14/2020 LOUIS ORTEGA
Coastal Zone Cleared 12/14/2020 LOUIS ORTEGA
ZA Case Cleared 12/14/2020 LOUIS ORTEGA
ZA Case Cleared 12/14/2020 LOUIS ORTEGA
ZI Cleared 12/14/2020 LOUIS ORTEGA
Low Impact Development Cleared 7/23/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/11/2021 TRACY TATE

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/20/2022 Corrections Issued AGUSTIN ALVAREZMORALES
Footing/Foundation/Slab 6/7/2022 Approved AGUSTIN ALVAREZMORALES
BUILDING-Rough-Frame 5/24/2023 Approved RYAN BARNES
METHANE-Rough 5/24/2023 Approved RYAN BARNES
Final 6/11/2024 Not Ready for Inspection RYAN BARNES
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Not Ready RYAN BARNES
Smoke Detectors 6/11/2024 Not Ready for Inspection RYAN BARNES
Final 6/24/2024 Permit Finaled ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Approved ANDREW BEELI
Smoke Detectors 6/24/2024 Approved ANDREW BEELI