13613 W TERRA BELLA ST 91331
Certificate Information: 13613 W TERRA BELLA ST 91331
- Application / Permit
- 20016-30000-02939
- Plan Check / Job No.
- B20WL00519
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ADU. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/19/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | TARIK SAOUD |
| Corrections Issued | 2/11/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 4/6/2020 | PARISA ZAHABI |
| Plan Check Approved | 4/20/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 4/21/2020 | APPLICANT |
| Issued | 5/19/2020 | LADBS |
| CofO in Progress | 1/12/2021 | MICHEL ABAJAN |
| Permit Finaled | 2/13/2021 | MICHAEL SMITH |
| CofO Issued | 2/13/2021 | MICHAEL SMITH |
| Permit Finaled | 2/13/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/25/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/25/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/25/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | My Town Building And Remodeling; Lic. No.: 1036847-B | 2807 W AVE M12 PALMDALE, CA 93551 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/29/2020 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/2/2020 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/25/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/9/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/23/2020 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/23/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 7/23/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/3/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/3/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/3/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/15/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/15/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/15/2020 | Approved | MICHEL ABAJAN |
| Insulation | 9/22/2020 | No Access for Inspection | DANIEL ORRANTE |
| Interior/Exterior Lathing | 9/22/2020 | No Access for Inspection | DANIEL ORRANTE |
| Insulation | 9/23/2020 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 9/23/2020 | Approved | DANIEL ORRANTE |
| Drywall Nailing | 10/5/2020 | Approved | MICHEL ABAJAN |
| Shower Pan | 10/5/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/23/2020 | Approved | MICHEL ABAJAN |
| Shower Pan | 10/23/2020 | Corrections Issued | MICHEL ABAJAN |
| Shower Pan | 10/26/2020 | Approved | MICHEL ABAJAN |
| Final | 1/11/2021 | OK to Issue CofO | MICHEL ABAJAN |
| MERV13>=Final | 1/11/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/11/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/11/2021 | Approved | MICHEL ABAJAN |